Hornsby Shire Council |
Attachment to Report No. CC32/09
Page 0 |
PLAN OF ACTION - OUTSTANDING KEY
ACTIONS
HORNSBY MALL STRATEGIC MANAGEMENT
PLAN
MAY 2009 to NOVEMBER
2009
STRATEGY ONE: LEADING HORNSBY MALL
INTO THE FUTURE
Action No. |
Action
Description |
Original Timeframe |
Action as
at 28 February 2009 |
1.1 (Priority One) |
Establish Hornsby Mall Leadership Group |
Medium term (6 months to 2 years) |
Council resolved in August
2006 (see Report No. CC 59/06) to act as interim Leadership Group. |
1.2 |
Establish Hornsby Mall Leadership Group Taskgroups |
Medium term (6 months to 2 years) |
Strategy
4 taskgroup - A Beautiful Hornsby Mall – actions are dependent on funding
opportunities identified in Council’s 2007-2011 Section 94 Plan. Taskgroup
will be formalised should Council approve funding to undertake beautification
of entrances to Mall as part of 2009/10 Management Plan. (see Key Action 4.1
below) |
STRATEGY TWO: A VIBRANT HORNSBY
MALL
Action No. |
Action
Description |
Original
Timeframe |
Action as
at 28 February 2009 |
2.1 (Priority Four) |
Image campaign |
Short term (0 to 6 months) |
Taskgroup investigating
alternate methods for completion of the Market survey. Revised completion
date now September 2009. |
STRATEGY THREE: A SAFE AND CLEAN
HORNSBY MALL
Action No. |
Action
Description |
Original
Timeframe |
Action as
at 28 February 2009 |
3.4 |
Monitoring |
Medium term (6 months to 2 years) |
At the March 2009
Ordinary Meeting (see Report No. CC 21/09) Council accepted in principle the CCTV
Sponsorship Proposal from Orion Integration Pty Ltd subject to Hornsby Police
undertaking Steps 6 to 11 of CCTV Guidelines and a further report outlining
inhouse costs of system being submitted and approved by Council. First draft
of Community Safety Plan to be presented to Community, Cultural and
Recreation Facilities Task Force Meeting by consultant at May 2009 meeting. |
3.6 |
Education Programs |
Medium term (6 months to 2 years) |
Meeting still to be held with President of
Business Chamber on “Biz Safe” program. Matter to be discussed at May 2009
Safety Group Meeting. |
STRATEGY FOUR: A BEAUTIFUL HORNSBY
MALL
Action No. |
Action
Description |
Original
Timeframe |
Action as
at 28 February 2009 |
4.1 |
Beautification of entrances |
Medium term (6 months to 2 years) |
Included for consideration
in the draft 2009/10 Management Plan for allocation of funds from 2007-2011
Section 94 Contributions Plan. |
MAY 2009 to
NOVEMBER 2009 CONT/.
STRATEGY SIX: A HORNSBY MALL THAT
FUNCTIONS WELL
Action No. |
Action Description |
Original
Timeframe |
Action as
at 28 February 2009 |
6.1 (Priority Six) |
Leasing of Public space |
Short term (0 to 6 months) |
Review of the Hornsby Mall
Code progressing. Completion expected
by June 2009. |
6.2 (Priority Six) |
Licences for public space |
Short term (0 to 6 months) |
Review of the Hornsby Mall
Code progressing. Completion expected by June 2009. |
6.3 |
Vehicle Access |
Medium term (6 months to 2 years) |
To be considered as part of
the review of the Hornsby Mall Code currently being undertaken under 6.1 and
6.2 above. |
6.5 (Priority Six) |
Permanent Markets |
Medium term (6 months to 2 years) |
To be considered as part of
the review of the Hornsby Mall Code presently being undertaken under 6.1 and
6.2 above. |
DECEMBER 2009 to NOVEMBER
2011
STRATEGY ONE: LEADING HORNSBY MALL
INTO THE FUTURE
Action No. |
Action
Description |
Original
Timeframe |
Action as
at 28 February 2009 |
1.4 (Priority Two) |
Develop a financial management plan for sustainable
funding solutions |
Medium term (6 months to 2 years) |
Plan to be developed for
respective key Actions following the establishment of the four taskgroups. At
this point in time only three taskgroups have been established. |
STRATEGY TWO: A VIBRANT HORNSBY
MALL
Action No. |
Action
Description |
Original
Timeframe |
Action as
at 28 February 2009 |
2.4 |
Small business joint
marketing venture |
Medium term (6 months to 2 years) |
Due to non attendance of
certain members at taskgroup meetings passport suggestion has not progressed.
Taskgroup to discuss at May 2009 meeting to discuss future action on this
item. |
STRATEGY THREE: A SAFE AND CLEAN
HORNSBY MALL
Action No. |
Action
Description |
Original
Timeframe |
Action as
at 28 February 2009 |
3.1 (Priority three) |
Hornsby Mall Ambassadors |
Medium term (6 months to 2 years) |
With funds identified for
the implementation of this action proposed for reallocation as part of the
2009/10 Management Plan, matter to be held in abeyance until further notice. |
STRATEGY FOUR: A BEAUTIFUL HORNSBY
MALL
Action No. |
Action
Description |
Original
Timeframe |
Action as
at 28 February 2009 |
4.2 |
Improved signage |
Medium term (6 months to 2 years) |
No action implemented at
this point in time. |
4.3 |
Landscaping |
Short term (0 to 6 months) |
Action to commence
following establishment of Strategy Four taskgroup. Provision made in Section
94 Contributions Plan 2007-2011. |
4.4 |
Public Seating |
Short term (0 to 6 months) |
Action to commence
following establishment of Strategy Four taskgroup. Provision made in Section
94 Contributions Plan 2007-2011. |
4.5 |
Community Art |
Medium term (6 months to 2 years) |
Draft Public Art Policy to
be reviewed by Hornsby Shire Arts Reference Committee. Report will now be
provided for Council’s consideration in late 2009. Matter to be held in
abeyance until adoption of Public Art Policy. |
DECEMBER 2011 AND
BEYOND
STRATEGY FIVE : DOING THE BUSINESS
IN HORNSBY MALL
Action No. |
Action
Description |
Original
Timeframe |
Action as
at 28 February 2009 |
5.1 |
Sustainable business practices |
Medium term (6 months to 2 years) |
Currently being implemented
in line with the framework associated with Council’s Sustainable Business
Strategy 2007-2010 and Economic Development Strategy 2007-2011. |
5.2 |
Shop front improvements |
Medium term (6 months to 2 years) |
Pilot program implemented
over Christmas 2007 to encourage shop front improvements in partnership with
Hornsby & District Chamber of Commerce and Industry Inc. |
5.3 |
Business Development Program |
Medium term (6 months to 2 years) |
Ongoing implementation
undertaken in association with Council’s Economic Development Strategy
2007-2011. |
5.4 |
Targeted tenancy strategy |
Medium term (6 months to 2 years) |
Business profiling
undertaken in partnership with Hornsby & District Chamber of Commerce and
Industry Inc. |
5.5 |
Inward investment |
Long term (2 years to 5 years) |
Currently being implemented
in line with the framework associated with Council’s Economic Development
Strategy 2007-2011. |
5.6 |
Local loyalty program |
Medium term (6 months to 2 years) |
No action implemented at
this point in time. |
5.7 |
Integrating |
Long term (2 to 5 years) |
A Masterplan for an
Integrated Town Centre proposed for completion as part of the 2009/10
Management Plan. . |