HSC_100K_NEW

 

 

ELECTRONIC BUSINESS PAPER

 

Local Planning Panel meeting

 

Friday 16 September 2022

at 11:00am

 

 

 


Hornsby Shire Council                                                   Agenda and Summary of Recommendations

Page 1

 

TABLE OF CONTENTS

ITEMS

Item 1     LPP55/22 DA/416/2020 - Further Report - Construction of a 10-12 Storey Mixed Use Development and Strata Subdivison - 228-234 Pacific Highway, Hornsby....................... 1

 


 


 

LPP Report No. LPP55/22

Local Planning Panel

Date of Meeting: 16/09/2022

 

1        DA/416/2020 - FURTHER REPORT - CONSTRUCTION OF A 10-12 STOREY MIXED USE DEVELOPMENT AND STRATA SUBDIVISON - 228-234 PACIFIC HIGHWAY, HORNSBY   

EXECUTIVE SUMMARY

DA No:

DA/416/2020 (Lodged on 2 June 2020)   

Description:

Construction of a 10-12 storey mixed use development comprising retail tenancies at the ground floor level, commercial tenancies at the first-floor level, a residential aged care facility at Levels 3-11, a residential apartment at Level 12 and strata subdivision

Property:

Lot A DP 304557 and Lot B DP 304557, Nos. 228-234 Pacific Highway, Hornsby

Applicant:

TBG Senior Living Services Pty Ltd

Owner:

TBG Senior Living Services Pty Ltd

Estimated Value:

$26,950,000

Ward:

B Ward

·              Development Application Number DA/416/2020 was reported to the Hornsby Local Planning Panel (the Panel) for determination on 27 July 2022.

·              The Panel deferred determination of the application to enable the applicant to prepare a revised clause 4.6 request that adequately addresses the relevant matters in Clause 4.6 with respect to the development standards proposed to be contravened and to provide a commentary on the strategic context of the site having regard to the draft Hornsby Town Centre Masterplan that is currently on exhibition.

·              The applicant has submitted a revised written request in accordance with Clause 4.6 ‘Exceptions to development standards’ of the Hornsby Local Environmental Plan 2013 to contravene the height of buildings development standard to address the matters raised by the Panel.  The submission is considered well founded and is supported.

Do not delete this line

RECOMMENDATION

THAT the Hornsby Local Planning Panel assume the concurrence of the Secretary of the Department of Planning and Environment pursuant to Clause 4.6 of the Hornsby Local Environmental Plan 2013 and approve Development Application No. DA/416/2020 for construction of a 10-12 storey mixed use development and strata subdivision at Lot A DP 304557, Lot B DP 304557, Nos. 228-234 Pacific Highway, Hornsby subject to the conditions of consent detailed in Schedule 1 of LPP Report No. LPP55/22.

Do not delete this line


 

BACKGROUND

On 27 July 2022, DA/416/2020 was reported to the Hornsby Local Planning Panel (the Panel) for determination. At that meeting, the Panel made the following resolution.

Accordingly, the Panel resolved to defer the determination of the application to enable the applicant to address the following matters:

1.         Preparation of a revised clause 4.6 request that adequately addresses the relevant matters in Clause 4.6 with respect to the development standards proposed to be contravened. Having regard to clause 4.6(4), the panel is not satisfied that the submission has satisfactorily addressed clause 4.6(3) and has not demonstrated that it is in the public interest through consistency with the objectives of the development standards (height and FSR).

2.         Provision of a commentary on the strategic context of the site having regard to the draft Hornsby Town Centre Masterplan that is currently on exhibition, which nominates the site as 12 storeys on the masterplan.

Upon receipt of the above information the Panel will determine the matter electronically at the next LPP meeting.

On 29 August 2022, the applicant provided a response to the Panel’s reasons for deferral.

response to reasons for deferral

1.         STRATEGIC CONTEXT

1.1        Draft Hornsby Town Centre Masterplan

In response to the Panel’s recommendation regarding commentary on the strategic context of the site having regard to the Hornsby Town Centre Masterplan currently on exhibition, the applicant has provided the following response:

“The Draft Masterplan is on public exhibition until 30 September 2022. The primary purpose of the Draft Masterplan is to facilitate the orderly increase of the existing population to accommodate approximately 4,500 additional dwellings and 5,000 new jobs by 2036.

The Draft Masterplan is not formally a matter for consideration pursuant to Section 4.15 of the Environmental Planning and Assessment Act 1979. Irrespective, the Draft Masterplan is of some relevance in relation to the circumstances of the case and/or “the public interest”.

The site is located at the southern edge of the Hornsby Town Centre, and the general Structure Plan seeks to retain and facilitate mixed-use land uses on the site. In terms of numeric controls, the Draft Masterplan recommends a 12-storey height control, and a minimum non-residential FSR control of 2:1. In the circumstances, the Draft Masterplan effectively seeks to increase the existing building height, maintain the employment generating capacity of the site, and accommodate a mix of residential and non-residential land uses.

The preferred building form for the site (circled in red) is diagrammatically depicted in the Draft Masterplan as follows:

A picture containing text

Description automatically generated

Diagram, engineering drawing

Description automatically generated

The proposed development has been designed under the direction of an urban design specialist (Karla Castellanos of [then] GMU Urban Design & Architecture), and has been carefully designed to accommodate the specific operational requirements of the proposed uses, whilst achieving a benchmark for high quality architecture within the Hornsby Town Centre.

The locality surrounding the site is undergoing a transition towards a more intensified precinct, with the newer development characterised by multi-storey mixed-use buildings. Further, the site effectively functions as the southern gateway to the Hornsby Town Centre, providing an opportunity to construct a high-quality building to be perceived as an important built form marker.

The Draft Masterplan recognises the important location of the site as the southern gateway to the Hornsby Town Centre, and proposes a building height of 12 storeys, with the diagrammatic images depicting a tower element extending above a base level podium.

In the circumstances, the proposed development is entirely consistent with the built form objectives of the Draft Masterplan, representing a contemporary expression of the desired future character of the locality.

Further, the proposed development has been designed to comply with the FSR control, and has intentionally redistributed the floor space to provide a more appropriate, vertical building form, that extends above the current building height control.

In the circumstances, the proposed development does not involve exceeding the development capacity of the site in terms of overall floor space, and the site is serviced by all necessary infrastructure.

The proposed “residential care facility” will generate employment for approximately 35 staff, with additional “flow on effects” arising due to the sites proximity to major retail and transport infrastructure, including Westfield Hornsby Shopping Centre and Hornsby Railway Station.

Further, the “residential care facility” (whilst technically a form of “residential accommodation”) will provide substantially more employment than any other form of “residential accommodation”, and substantially more employment than the approved residential apartments on the site.

The site has extremely good access to public transport and is within 400 metres walking distance of Hornsby Railway Station. The site is located approximately 1.5 kilometres from Hornsby Ku-ring-gai Hospital, approximately 3 kilometres from Neringah Hospital, and approximately 2.4 kilometres from Mount Wilga Private Rehabilitation Hospital.

Finally, the site is located directly opposite the main pedestrian entrance to Westfield Hornsby Shopping Centre, circumstances in which the future residents of the facility will have excellent access to a full range of services and facilities, and contribute significantly to the stimulation of the local economy.

In summary, the proposed development is consistent with the overall objectives of the Draft Masterplan, and will make a significant contribution to the quality of architecture and mix of land uses within the Hornsby Town Centre.”

Council concurs with the Applicants response in that the proposal would be consistent with the draft masterplan currently on exhibition which recommends a 12-storey height control, a minimum non-residential FSR control of 2:1 and continuation of a mix of residential and non-residential land uses.

2.         STATUTORY CONTROLS

Section 4.15(1)(a) requires Council to consider “any relevant environmental planning instruments, draft environmental planning instruments, development control plans, planning agreements and regulations”.

2.1        Clause 4.6 written submission

At the Hornsby Local Planning Panel meeting held on 27 July 2022, the Panel considered the Clause 4.6 submission and were not satisfied that the applicant’s written request had adequately addressed the matters required to be demonstrated in clause 4.6(3) of the Hornsby Local Environmental Plan 2013 (HLEP). Furthermore, in accordance with clause 4.6(4) of the HLEP, the Panel were not satisfied that the proposed development would be in the public interest because it has not been demonstrated through the Clause 4.6 submission that it is consistent with the objectives of the ‘Height of Buildings’ development standard, the ‘Floor Space Ratio’ development standard and the objectives for development within the zone in which the development is proposed to be carried out.

In response to point 1 of the Panel’s deferral reasons, the applicant has submitted a revised Clause 4.6 written request which is addressed below.

2.1.1     Exceptions to Development Standards

The application has been assessed against the requirements of Clause 4.6 of the HLEP.  This clause provides flexibility in the application of development standards in circumstances where strict compliance with those standards would, in any particular case, be unreasonable or unnecessary, and it can be demonstrated that sufficient environmental planning grounds are present to justify contravening a development standard.

The application seeks to contravene Clause 4.3 of the HLEP as the maximum height of building development standard as the roof pitch would be 39.58m which exceeds the development standard by 16.08m or 68% and does not comply with the 23.5m height of building development standard.

The objectives of Clause 4.3 Height of buildings are as follows:

(a)        To permit a height of buildings that is appropriate for the site constraints, development potential and infrastructure capacity of the locality.

(b)        The height of a building on any land is not to exceed the maximum height shown for the land on the Height of Buildings Map.

In addition, the application seeks to contravene Clause 4.4(2A) of the HLEP which states that a maximum Floor Space Ratio of 2:1 applies for any residential accommodation for the subject site as the proposed development provides a residential FSR of 3:95:1. 

The objectives of Clause 4.4 Floor Space Ratio are as follows:

(a)      To permit development of a bulk and scale that is appropriate for the site constraints,        development potential and infrastructure capacity of the locality.      

The applicant has made a submission in support of the contravention to the development standard in accordance with Clause 4.6 of the HLEP. Clause 4.6 provides that development consent must not be granted for development that contravenes a development standard unless the consent authority has considered a written request from the applicant that seeks to justify the contravention of the development standard by demonstrating:

(a)        That compliance with the development standard is unreasonable or unnecessary in the circumstances of the case.

(b)        That there are sufficient environmental planning grounds to justify contravening the development standard.

Council must be satisfied that the written request provided by the applicant under Clause 4.6 addresses both the unreasonable and unnecessary test and demonstrates sufficient environmental planning grounds to justify contravening the development standard. These matters are discussed below.

2.1.1.1  Unreasonable or Unnecessary Clause 4.6(3)(a)

There are five common methods by which an applicant can demonstrate that compliance with a development standard is unreasonable or unnecessary in the circumstances of the development. Initially proposed for objections under clause 6 of SEPP 1 in the decision of Wehbe v Pittwater Council [2007] NSWLEC 827 Pearson C summarised and applied these methods to written requests made under Clause 4.6 in Four2Five Pty Ltd v Ashfield Council [2015] NSWLEC 1009 [61-62]. These five methods are generally as follows:

·              The objectives of the development standard are achieved notwithstanding non-compliance with the standard.

·              The underlying objective or purpose is not relevant to the development.

·              That the objective would be defeated or thwarted if compliance was required.

·              That the development standard has been virtually abandoned or destroyed by the Council’s own actions in departing from the standard.

·              The zoning of the land is unreasonable or inappropriate.

It is not required to demonstrate that a development meets multiple methods as listed above, and the satisfaction of one can be adequate to demonstrate that the development standard is unreasonable or unnecessary.

The amended written request prepared by James Lovell and Associates, dated 25 August 2022 provides a detailed assessment of the proposal with respect to the development standards sought to be contravened. The request argues that:

Height of Building

What is the underlying object or purpose of the standard

·              The locality surrounding the site is undergoing a transition towards a more intensified precinct, with the newer development characterised by multi-storey mixed-use buildings. Further, the site effectively functions as the southern gateway to the Hornsby Town Centre, providing an opportunity to construct a high-quality building to be perceived as an important built form marker. In that regard, the proposed development has been designed under the direction of an urban design specialist (Karla Castellanos of [then] GMU Urban Design & Architecture), and has been carefully designed to accommodate the specific operational requirements of the proposed uses, whilst achieving a benchmark for high quality architecture within the Hornsby Town Centre.

·              The applicable building height and floor space ratio (FSR) controls incorporated in the LEP effectively generate a “squat building form” which, in terms of design quality, is inherently inappropriate for a prominent gateway site.

·              Accordingly, the proposed development has been designed to comply with the FSR control, and has intentionally redistributed the floor space to provide a more appropriate, vertical building form, that extends above the current building height control.

·              The proposed development does not involve exceeding the development capacity of the site in terms of overall floor space, and the site is serviced by all necessary infrastructure.

·              Further, the proposed building form, including the variation to the building height control, has specifically been designed to achieve a building form that is more appropriate for the site having regard to its physical context, and the nature of surrounding development.

·              In the circumstances, the proposed development is consistent with the objective of the building height control, notwithstanding the numerical variation.

The objectives of the standard are achieved notwithstanding non-compliance with the standard

·              The proposed development is consistent with the objective of the building height control, notwithstanding the numerical variation. In that regard, the Applicant relies upon ground 1 in Wehbe (i.e. the objectives and purposes of the standard are achieved notwithstanding non-compliance with the development standard) to support its submission that compliance with the development standard is both unreasonable and unnecessary in the circumstances of this case.

·              Further, the proposed development has intentionally been designed to provide a more appropriate, vertical building form, that extends above the building height control.

·              The proposed building form is considered substantially more appropriate for the site than a compliant “squat building form” having regard to the specific locational characteristics of the site, functioning as the southern gateway to the Hornsby Town Centre.

·              In that regard, the Draft Hornsby Town Centre Masterplan recognises the important location of the site as the southern gateway to the Hornsby Town Centre, and proposes a building height of 12 storeys, with the diagrammatic images depicting a tower element extending above a base level podium. In the circumstances, the proposed development is entirely consistent with the built form objectives of the Draft Masterplan, representing a contemporary expression of the desired future character of the locality.

The underlying objective or purpose of the standard is not relevant to the development and therefore compliance is unnecessary

·              The objectives and purpose of the building height control remain relevant, and the proposed development is consistent with the objective of the building height control, notwithstanding the numerical variation.

The underlying object or purpose would be defeated or thwarted if compliance was required and therefore compliance is unreasonable

·              The proposed development is consistent with the objective of the building height control, notwithstanding the numerical variation. Further, strict compliance with the building height control would generate a “squat building form” which, in terms of design quality, is inherently inappropriate for a prominent gateway site.

·              In addition, the Draft Hornsby Town Centre Masterplan proposes a building height of 12 storeys, with the diagrammatic images depicting a tower element extending above a base level podium. In the circumstances, the proposed development is entirely consistent with the built form objectives of the Draft Masterplan, representing a contemporary expression of the desired future character of the locality.

The development standard has been virtually abandoned or destroyed by the council’s own actions in granting consents departing from the standard and hence compliance with the standard is unnecessary and unreasonable

·              The building height control has not been abandoned or destroyed by the Council’s actions. However, the Council has consistently adopted an orderly but flexible approach to the implementation of development standards in appropriate circumstances, including when the objectives of the standard are achieved, notwithstanding numerical variations. Further, the objectives of Clause 4.6 of the LEP includes to provide “an appropriate degree of flexibility in applying certain development standards to particular development”.

·              Again, the proposed development is entirely consistent with the built form objectives of the Draft Masterplan, representing a contemporary expression of the desired future character of the locality.

Compliance with the development standard is unreasonable or inappropriate due to existing use of land and current environmental character of the particular parcel of land. That is, the particular parcel of land should not have been included in the zone

·              The zoning of the land remains relevant and appropriate, and the proposed development is consistent with (and not antipathetic to) the objectives of the B4 - Mixed Use zone.

Floor Space Ratio

What is the underlying object or purpose of the standard

·              Further, it is reasonable to conclude that the residential FSR control is intended to ensure that development makes an appropriate contribution to employment generation and business activity within certain specific localities.

·              The locality surrounding the site is undergoing a transition towards a more intensified precinct, with the newer development characterised by multi-storey mixed-use buildings. Further, the site effectively functions as the southern gateway to the Hornsby Town Centre, providing an opportunity to construct a high-quality building to be perceived as an important built form marker.

·              In that regard, the proposed development has been designed under the direction of an urban design specialist (Karla Castellanos of [then] GMU Urban Design & Architecture), and has been carefully designed to accommodate the specific operational requirements of the proposed uses, whilst achieving a benchmark for high quality architecture within the Hornsby Town Centre.

·              The applicable building height and floor space ratio (FSR) controls incorporated in the LEP effectively generate a “squat building form” which, in terms of design quality, is inherently inappropriate for a prominent gateway site. Accordingly, the proposed development has been designed to comply with the FSR control, and has intentionally redistributed the floor space to provide a more appropriate, vertical building form, that extends above the current building height control.

·              In the circumstances, the proposed development does not involve exceeding the development capacity of the site in terms of overall floor space, and the site is serviced by all necessary infrastructure.

·              In relation to the expressed objective of the FSR control, the proposed development complies with the total FSR control, circumstances in which the bulk and scale of the building is an appropriate response to the site constraints, development potential and infrastructure capacity of the locality.

·              In relation to the assumed objective of the residential FSR control, the proposed “residential care facility” will generate employment for approximately 35 staff, with additional “flow on effects” arising due to the sites proximity to major retail and transport infrastructure, including Westfield Hornsby Shopping Centre and Hornsby Railway Station.

·              Finally, the “residential care facility” (whilst technically a form of “residential accommodation”) will provide substantially more employment than any other form of “residential accommodation”, and substantially more employment than the approved residential apartments on the site.

·              In the circumstances, the proposed development is consistent with both the expressed and assumed objectives of the residential FSR control, notwithstanding the numerical variation.

The objectives of the standard are achieved notwithstanding non-compliance with the standard

·              As noted above, the proposed development is consistent with both the expressed and assumed objectives of the residential FSR control, notwithstanding the numerical variation.

·              In that regard, the Applicant relies upon ground 1 in Wehbe (i.e. that the objectives and purposes of the standard are achieved notwithstanding non-compliance with the development standard) to support its submission that compliance with the development standard is both unreasonable and unnecessary in the circumstances of this case.

·              The proposed development does not involve exceeding the development capacity of the site in terms of overall floor space, and the site is serviced by all necessary infrastructure.

·              Further, the proposed “residential care facility” will generate employment for approximately 35 staff, with additional “flow on effects” arising due to the sites proximity to major retail and transport infrastructure, including Westfield Hornsby Shopping Centre and Hornsby Railway Station.

·              In the circumstances, the “residential care facility” (whilst technically a form of “residential accommodation”) will provide substantially more employment than any other form of “residential accommodation”, and substantially more employment than the approved residential apartments on the site.

The underlying objective or purpose of the standard is not relevant to the development and therefore compliance is unnecessary.

·              The objectives and purpose of the residential FSR control remain relevant, and the proposed development is consistent with both the expressed and assumed objectives of the residential FSR control, notwithstanding the numerical variation.

The underlying object or purpose would be defeated or thwarted if compliance was required and therefore compliance is unreasonable.

·              The proposed development is consistent with both the expressed and assumed objectives of the residential FSR control, notwithstanding the numerical variation.

·              Further, strict compliance with the non-residential FSR control would require a not insignificant proportion of the “residential care facility” to be converted to an alternate use, and thereby the significant public, health and economic benefits arising from the inclusion of that important use would be unnecessarily lost.

The development standard has been virtually abandoned or destroyed by the council’s own actions in granting consents departing from the standard and hence compliance with the standard is unnecessary and unreasonable.

·              The non-residential FSR control has not been abandoned or destroyed by the Council’s actions. However, the Council has consistently adopted an orderly but flexible approach to the implementation of development standards in appropriate circumstances, including when the objectives of the standard are achieved, notwithstanding numerical variations.

·              In that regard, the “residential care facility” (whilst technically a form of “residential accommodation”) will provide substantially more employment than any other form of “residential accommodation”, and substantially more employment than the approved residential apartments on the site.

·              Further, the objectives of Clause 4.6 of the LEP includes to provide “an appropriate degree of flexibility in applying certain development standards to particular development”.

Compliance with the development standard is unreasonable or inappropriate due to existing use of land and current environmental character of the particular parcel of land. That is, the particular parcel of land should not have been included in the zone.

·              The zoning of the land remains relevant and appropriate and the proposed development is consistent with (and not antipathetic to) the objectives of the B4 - Mixed Use zone.

Council considers that the applicant’s amended written request sufficiently identifies that the objectives of the development standard are achieved notwithstanding non-compliance with the standard.

The request makes a sufficient argument that the proposed FSR and increased height are appropriate for the site and consistent with the business zoning of the site and the objectives of the height and FSR development standards for the site.  The contravention would not be out of character when viewed from the public domain and would not result in amenity impacts to adjoining properties in terms of overshadowing, views or outlook.

The request provides a sufficient planning argument that the proposed development was intentionally designed to breach the building height control to provide a slender tower instead of a bulky building with a large courtyard located on the two storey podium level instead of the rooftop or a confined narrow area. The request argues that the breach in height was guided by the Hornsby Design Excellence Committee who unanimously support the proposal instead of the previous approved building.  Whilst technical compliance could be achieved with the height provision, it would result in a bulky building footprint which does not maximise the development potential for the site and would result in an inferior design.  It is also noted that the current design is consistent with the draft Hornsby Town Centre Masterplan currently on exhibition which proposes a building height of 12 storeys at the subject site with a tower element.

The request makes a sufficient planning argument that the proposed “residential care facility” will generate employment for approximately 35 staff and that the “residential care facility” (whilst technically a form of “residential accommodation”) will provide substantially more employment than any other form of “residential accommodation”, and substantially more employment than the approved mixed use development application on the site which meets the objectives of the FSR development standard.

It is also noted that neither the Height of Building or non-residential FSR would not generate additional infrastructure demand and does not amount to an overdevelopment of the site noting that the proposal complies with the overall FSR for the site.  The non-compliance could be avoided by strictly complying with the height of building standard or non-residential FSR, however this would not result in a better architectural outcome to that of the approved design which was unanimously supported by the Hornsby Design Excellence Panel and would not achieve the development potential for the site or achieve residential aged care with ongoing job creation in the town centre.

Accordingly, it is considered that the proposal is consistent with the objectives of the B4 zone as the development provides for a mixture of compatible land uses which integrates business, office, retail and residential in an accessible location to maximise public transport patronage and satisfies the objective of the height of building and floor space ratio development standards.

It is considered that the development potential and infrastructure capacity of the locality are capable of accommodating a development of the kind proposed.

2.1.1.2  Environmental Planning Grounds

In addition to demonstrating that compliance is unreasonable or unnecessary, Clause 4.6(3)(b) of the HLEP requires that there are sufficient environmental planning grounds to justify contravening the development standard. In demonstrating that sufficient environmental planning grounds exist, it must be demonstrated that the planning grounds are particular to the circumstances of the development on the subject site (summarised from Four2Five Pty Ltd v Ashfield Council [2015] NSWLEC 1009 [60].

In demonstrating the environmental planning grounds the written request states:

Height of Building

·              Clause 48 of SEPP (Housing for Seniors or People with a Disability) 2004 does not specify a maximum building height, and there is no maximum building height control for a “residential care facility”;

·              The applicable building height and FSR controls incorporated in the LEP effectively generate a “squat building form” which, in terms of design quality, is inherently inappropriate for a prominent gateway site;

·              The proposed development has been designed to comply with the FSR control, and has intentionally redistributed the floor space to provide a more appropriate, vertical building form, that extends above the current building height control;

·              The proposed development does not involve exceeding the development capacity of the site in terms of overall floor space, and the site is serviced by all necessary infrastructure;

·              The compliance with the total FSR control of 5:1 ensures the proposed development the bulk and scale of the building is an appropriate response to the site constraints, development potential and infrastructure capacity of the locality;

·              Strict compliance with the building height control would generate a “squat building form” which, in terms of design quality, is inherently inappropriate for a prominent gateway site;

·              The proposed building form, including the variation to the building height control, has specifically been designed to achieve a building form that is more appropriate for the site having regard to its physical context, and the nature of surrounding development;

·              The Draft Hornsby Town Centre Masterplan proposes a building height of 12 storeys, with the diagrammatic images depicting a tower element extending above a base level podium. In the circumstances, the proposed development is entirely consistent with the built form objectives of the Draft Masterplan, representing a contemporary expression of the desired future character of the locality;

·              The proposed development has been carefully designed to respect the existing and desired future character and built form of the surrounding locality, and respect the location of the site as an important southern gateway to the town centre;

·              The site is adjoined to the south by the railway corridor, and providing a base level podium below a vertical tower element facilitates greater setback from the railway corridor;

·              The provision of a basement podium and tower element facilitates the provision of useable communal open space that would not otherwise be available in a “squat building form” involving a substantially larger building footprint above the podium level;

·              The proposed development is consistent with (and not antipathetic to) the objectives of the B4 - Mixed Use zone; and

·              The proposed development is consistent with the objective of the building height control, notwithstanding the numerical variation.

Floor Space Ratio

·              The LEP specifies a maximum FSR of 5:1, and the proposed development provides an FSR of 5:1;

·              The compliance with the total FSR control of 5:1 ensures the proposed development the bulk and scale of the building is an appropriate response to the site constraints, development potential and infrastructure capacity of the locality;

·              The proposed development complies with Clause 19 of the SEPP which species that development for the purposes of seniors housing should not include the use of any part of the ground floor level of a building that fronts a street for residential purposes if the building is located on land zoned primarily for commercial purposes;

·              Clause 19 of the SEPP does not require any additional non-residential floor space to be located above the ground floor level, even on sites zoned primarily for commercial purposes;

·              The proposed development has been carefully designed to respect the existing and desired future character and built form of the surrounding locality, and respect the location of the site as an important southern gateway to the town centre;

·              The Draft Hornsby Town Centre Masterplan proposes a building height of 12 storeys, with the diagrammatic images depicting a tower element extending above a base level podium. In the circumstances, the proposed development is entirely consistent with the built form objectives of the Draft Masterplan, representing a contemporary expression of the desired future character of the locality;

·              The proposed “residential care facility” will generate employment for approximately 35 staff, with additional “flow on effects” arising due to the sites proximity to major retail and transport infrastructure, including Westfield Hornsby Shopping Centre and Hornsby Railway Station;

·              The “residential care facility” (whilst technically a form of “residential accommodation”) will provide more employment than any other form of “residential accommodation”, and substantially xxiii more employment than the approved residential apartments on the site;

·              Strict compliance with the residential FSR control would require a not insignificant proportion of the “residential care facility” to be converted to an alternate use, and thereby the significant public, health and economic benefits arising from the inclusion of that important use would be unnecessarily lost;

·              The site has extremely good access to public transport and is within 400 metres walking distance of Hornsby Railway Station. The site is located approximately 1.5 kilometres from Hornsby Ku-ring-gai Hospital, approximately 3 kilometres from Neringah Hospital, and approximately 2.4 kilometres from Mount Wilga Private Rehabilitation Hospital;

·              The site is located directly opposite the main pedestrian entrance to Westfield Hornsby Shopping Centre, circumstances in which the future residents of the facility will have excellent access to a full range of services and facilities, and contribute significantly to the stimulation of the local economy;

·              The variation to the residential FSR does not alter the proposed building forms, circumstances in which there are no consequences arising in terms of the physical relationship and/or amenity of surrounding properties;

·              The proposed development is consistent (and not antipathetic to) the objectives of the B4 - Mixed Use zone; and

·              The proposed development is consistent with both the expressed and assumed objectives of the residential FSR control, notwithstanding the numerical variation.

Council considers that the environmental planning grounds stated within the amended written request are sufficient with respect to Clause 4.6(3)(b) and that the stated grounds are specific to the proposed development and the circumstances of the development site.

The proposed development the proposed building form, including the variation to the residential FSR control, has specifically been designed to achieve a building form that is more appropriate for the site having regard to its physical context, and the nature of surrounding development. The proposal incorporates a slender building compared to that previously approved for the site, generates ongoing employment throughout all hours of the day and does not create unreasonable environmental impacts to adjoining development with regard to visual bulk, overshadowing, amenity or privacy.

It is therefore considered that the written request adequately demonstrates compliance with the clause and is acceptable in this regard.

Council further notes that in demonstrating the unreasonable and unnecessary test, the applicant further established environmental planning grounds with respect to the site and the surrounding constraints.

2.1.1.3  Public Interest and Clause 4.6(4)

Clause 4.6(4) states that development consent must not be granted for development that contravenes a development standard unless:

(a)        The consent authority is satisfied that -

(i)         The applicant’s written request has adequately addressed the matters required to be demonstrated by subclause (3), and

(ii)         The proposed development will be in the public interest because it is consistent with the objectives of the particular standard and the objectives for development within the zone in which the development is proposed to be carried out, and

(b)        The concurrence of the Planning Secretary has been obtained.

With regard to part (a)(i), the written request is considered to adequately address the matter required to be demonstrated as outlined above.

With regard to part (a)(ii), the proposed development is considered to be in the public interest because it is consistent with the objectives of the particular standard and the objectives for development within the zone in which the development is proposed to be carried out.

With regard to (b), on 21 February 2018, the Secretary of the Department of Planning and Environment issued a Notice under cl. 64 of the Environmental Planning and Assessment Regulation 2000. The Secretary’s concurrence may not be assumed by a delegate of council if:

·              The development contravenes a numerical standard by greater than 10%.

·              The variation is to a non-numerical standard.

Local Planning Panels constituted under the Environmental Planning and Assessment Act 1979 exercise consent authority functions on behalf of a Council and are not delegates of Council. Therefore, Local Planning Panels may determine a development application notwithstanding, a numerical non-compliance in excess of 10%.

Accordingly, it is considered that the amended Request satisfactorily responds to the relevant matters required to be addressed under Clause 4.6 and that the Panel, as consent authority, may rely upon the Request and grant development consent to the DA. Should the Panel resolve to approve the DA, it should also provide a statement in the reasons for approval that it has satisfied itself of the matters in Clause 4.6(4).

CONCLUSION

The application proposes construction of a 10-12 storey mixed use development comprising retail tenancies at the ground floor level, commercial tenancies at the first-floor level, a residential aged care facility at Levels 3-11, a residential apartment at Level 12 and strata subdivision.

The development generally meets the desired outcomes of Council’s planning controls and is satisfactory having regard to the matters for consideration under Section 4.15 of the Environmental Planning and Assessment Act 1979.

Council received 6 submissions during the public notification period. The matters raised have been addressed in the original assessment report.

Having regard to the circumstances of the case, approval of the application is recommended.

The reasons for this decision are:

·              The request under Clause 4.6 of Hornsby Local Environmental Plan 2013 to contravene the ‘Height of buildings’ development standard is well founded. Strict compliance with the development standard is considered unreasonable and unnecessary in the circumstances of the case and sufficient environmental planning grounds have been submitted to justify the contravention to the development standard.

·              The proposed development generally complies with the requirements of SEPP (Housing for Seniors or People with a Disability) 2004 and the Hornsby Development Control Plan 2013.

·              The proposed development does not create unreasonable environmental impacts to adjoining development with regard to visual bulk, overshadowing, amenity or privacy.

Note:  At the time of the completion of this planning report, no persons have made a Political Donations Disclosure Statement pursuant to Section 10.4 of the Environmental Planning and Assessment Act 1979 in respect of the subject planning application.

RESPONSIBLE OFFICER

The officer responsible for the preparation of this report is Matthew Miles.

 

 

 

 

 

 

Cassandra Williams

Major Development Manager - Development Assessments

Planning and Compliance Division

 

 

 

 

Rod Pickles

Manager - Development Assessments

Planning and Compliance Division

 

 

 

 

Attachments:

1.

Locality Plan

 

 

2.

Assessment Report

 

 

3.

Response to Hornsby Draft Masterplan

 

 

4.

Revised Clause 4.6 (Height of Building)

 

 

5.

Revised Clause 4.6 (FSR)

 

 

6.

Architectural Plans

 

 

7.

Landscape Plans

 

 

 

 

File Reference:           DA/416/2020

Document Number:     D08482164

 


SCHEDULE 1

1.         Deferred Commencement

a)         Pursuant to Section 4.16(3) of the Environmental Planning and Assessment Act 1979, this consent does not operate until a signed deed of agreement between the subject property owner and adjoining property at Strata Scheme No. 30399, situated at No. 10-12 Edgeworth David Avenue, Hornsby for the closure of access area during construction and restriction of access has been created.

b)         Such information must be submitted within 36 months of the date of this notice.

Upon Council’s written satisfaction of the above information, the following conditions of development consent apply:

GENERAL CONDITIONS

The conditions of consent within this notice of determination have been applied to ensure that the use of the land and/or building is carried out in such a manner that is consistent with the aims and objectives of the relevant legislation, planning instruments and Council policies affecting the land and does not disrupt the amenity of the neighbourhood or impact upon the environment.

Note:  For the purpose of this consent, the term ‘applicant’ means any person who has the authority to act on or the benefit of the development consent.

Note:  For the purpose of this consent, any reference to an Act, Regulation, Australian Standard or publication by a public authority shall be taken to mean the gazetted Act or Regulation, or adopted Australian Standard or publication as in force on the date that the application for a construction certificate is made.

2.         Approved Plans and Supporting Documentation

The development must be carried out in accordance with the plans and documentation listed below and endorsed with Council’s stamp, except where amended by Council and/or other conditions of this consent:

Approved Plans

Plan No.

Plan Title

Drawn by

Dated

Council Reference

DA-01R, R

Site location plan

Coble Stephens Architects

07.02.2022

 

DA-38R, Q

Detail Section

Coble Stephens Architects

21.07.2021

 

DA-44R, R

Detail Section

Coble Stephens Architects

07.02.2022

 

DA-41R, R

Site plan - 11KV Blowout

Coble Stephens Architects

07.02.2022

 

DA-32R, Q

Railway corridor elevations

Coble Stephens Architects

21.07.2021

 

DA-37R, R

Site plan - ground floor

Coble Stephens Architects

07.02.2022

 

DA-39R, R

Garbage enclosure

Coble Stephens Architects

07.02.2022

 

DA-34R, Q

Detail plans - loading dock

Coble Stephens Architects

21.07.2021

 

DA-40R, R

Site plan - 33KV Blowout

Coble Stephens Architects

07.02.2022

 

DA-19R, R

North elevation

Coble Stephens Architects

07.02.2022

 

DA-20R, R

South elevation

Coble Stephens Architects

07.02.2022

 

DA-22R, R

West elevation

Coble Stephens Architects

07.02.2022

 

DA-26R, R

Section D-D

Coble Stephens Architects

07.02.2022

 

DA-25R, R

Section C-C

Coble Stephens Architects

07.02.2022

 

DA-21R, R

East elevation

Coble Stephens Architects

07.02.2022

 

DA-24R, R

Section B-B

Coble Stephens Architects

07.02.2022

 

DA-23R, R

Section A-A

Coble Stephens Architects

07.02.2022

 

DA-14R, R

Level 11 floor plan

Coble Stephens Architects

07.02.2022

 

DA-15R, R

Roof plan

Coble Stephens Architects

07.02.2022

 

DA-16R, R

Basement 1

Coble Stephens Architects

07.02.2022

 

DA-18R, R

Basement 03

Coble Stephens Architects

07.02.2022

 

DA-17R, R

Basement 02

Coble Stephens Architects

07.02.2022

 

DA-08R, R

Fifth floor plan

Coble Stephens Architects

07.02.2022

 

DA-09R, R

Level 6 floor plan

Coble Stephens Architects

07.02.2022

 

DA-10R, R

Level 7 floor plan

Coble Stephens Architects

07.02.2022

 

DA-11R, R

Level 8 floor plan

Coble Stephens Architects

07.02.2022

 

DA-12R, R

Level 9 floor plan

Coble Stephens Architects

07.02.2022

 

DA-13R, R

Level 10 floor plan

Coble Stephens Architects

07.02.2022

 

DA-05R, R

Level 2 floor plan

Coble Stephens Architects

07.02.2022

 

DA-07R, R

Level 4 floor plan

Coble Stephens Architects

07.02.2022

 

DA-06R, R

Level 3 floor plan

Coble Stephens Architects

07.02.2022

 

DA-03R, R

Ground floor plan

Coble Stephens Architects

07.02.2022

 

DA-04R, R

Level 1 floor plan

Coble Stephens Architects

07.02.2022

 

DA-02R, R

Site plan

Coble Stephens Architects

07.02.2022

 

L-01, Rev D

Landscape plan Ground floor 

Space Landscape Designs

22/3/2022

 

L-02, Rev D

Landscape plan Level 1

Space Landscape Designs

22/3/2022

 

L-03, Rev E

Landscape plan Level 2

Space Landscape Designs

22/3/2022

 

L-04, Rev D

Landscape plan Level 3-9 

Space Landscape Designs

22/3/2022

 

L-05, Rev D

Landscape plan Level 10 

Space Landscape Designs

22/3/2022

 

L-06, Rev E

Landscape plan Level 11 

Space Landscape Designs

22/3/2022

 

Supporting Documentation

Document Title

Prepared by

Dated

Council Reference

Sydney Trains Concurrence Conditions

Sydney Trains

27/06/2022

D08441310

TfNSW Concurrence Conditions

TfNSW

5/05/2022

D08402145

TfNSW Concurrence Conditions for CTMP

TfNSW

27/04/2022

D08396831

Disability Access Report

Cheung Access

6/04/2022

D08398418

Acoustic Report

Acoustic works

28/04/2022

D08398632

Geotech report

Douglas Partners

April 2022

D08395490

Rail impact Assessment

Douglas Partners

April 2022

D08395495

Stormwater plans, basement 2 and 3, SW001, Rev 8

Majcon

23/03/2022

D08377775

Stormwater plans, basement 1 and ground floor, SW002, Rev 8

Majcon

23/03/2022

D08377775

Stormwater plans, level 1, SW003, Rev 8

Majcon

23/03/2022

D08377775

Sediment erosion plans, ER001, ER002, ER003, Rev 07

Majcon

23/03/2022

D08377774

Sediment erosion plan ER004, Rev 02

Majcon

23/03/2022

D08377774

Survey plan, 122-02, Rev 03

Craig and Rhodes

11/03/2022

D08369631

Construction Traffic Management Plan, Rev I

Transport and traffic planning

March 2022

D08365757

Detailed Site Investigation, Ref 99895.01

Douglas Partners

17/12/21

D08367320

BCA Report, Rev 2

Custom Development Certifications

29/05/2022

D08418718

BCA Letter

Holmes Fire

19/05/2022

D08418718

Traffic and parking impact assessment, Issue J

Transport and traffic planning

May 2022

D08416252

Survey, Sheet 1 to 2, Rev 03

Craig and Rhodes

11/03/2022

D08369631

Site retention design report

Majcon Consulting

20/05/2022

D08443588

Civil and structural design plans, SR0 rev E, SR1 rev B, SR2 rev B, SR 3 rev B, SR 4, rev B, SR 5 rev F, SR6 rev C

Majcon Consulting

June 2021

D08443632

Electrical Blowout Design Report

ECL Power Services

30 July 2021

D08390336

Electrical Blowout Plan

ECL Power Services

30 July 2021

D08390335

Plans prepared and certified by Craig & Rhodes sheets 1, 3, 4

Craig & Rhodes

23/03/2022

D08443594

Plans prepared and certified by Craig & Rhodes sheets 5, 6, 7, 8

Craig & Rhodes

23/03/2022

D08443598

3.         Section 7.11 Development Contributions

a)         In accordance with Section 4.17(1) of the Environmental Planning and Assessment Act 1979 and the Hornsby Shire Council Section 7.11 Development Contributions Plan 2020-2030, the following monetary contributions must be paid to Council to cater for the increased demand for community infrastructure resulting from the development:

Description

Contribution (4)

Roads

$135,355.75

Open Space and Recreation

$11,537.35

Community Facilities

$7,105.95

Plan Preparation and Administration

$769.95

TOTAL

$154,769.00

being for 1 x 3+ bedroom unit, 306m2 of retail floor space and 520m2 of business floor space.

b)         The value of this contribution is current as at 12 July 2022. If the contribution is not paid within the financial quarter that this condition was generated, the contribution payable will be adjusted in accordance with the provisions of the Hornsby Shire Council Section 7.11 Development Contributions Plan and the amount payable will be calculated at the time of payment in the following manner:

$CPY   =   $CDC  x CPIPY

CPIDC

Where:

$CPY     is the amount of the contribution at the date of Payment

$CDC     is the amount of the contribution as set out in this Development Consent

CPIPY    is the latest release of the Consumer Price Index (Sydney - All Groups) at the date of Payment as published by the ABS.

CPIDC    is the Consumer Price Index (Sydney - All Groups) for the financial quarter at the date applicable in this Development Consent Condition.

c)         The monetary contribution must be paid to Council:

i)          Prior to the issue of the Subdivision Certificate where the development is for subdivision; or

ii)          Prior to the issue of the first Construction Certificate where the development is for building work; or

iii)         Prior to issue of the Subdivision Certificate or first Construction Certificate, whichever occurs first, where the development involves both subdivision and building work; or

iv)         Prior to the works commencing where the development does not require a Construction Certificate or Subdivision Certificate.

Note: It is the professional responsibility of the Principal Certifying Authority to ensure that the monetary contributions have been paid to Council in accordance with the above timeframes.

Note: In accordance with Ministerial Directions, the payment of contribution fees for development with a cost of works of over $10 million can be deferred to prior to Occupation Certificate.

Note: Council’s Development Contributions Plan may be viewed at www.hornsby.nsw.gov.au or a copy may be inspected at Council’s Administration Centre during normal business hours.

4.         Construction Certificate

a)         A Construction Certificate is required to be approved by Council or a Private Certifying Authority prior to the commencement of any construction works under this consent.

b)         A separate Works Certificate must be obtained from Council for all works within the public road reserve under S138 of the Roads Act 1993.

c)         The Construction Certificates plans must be consistent with the Development Consent plans.

REQUIREMENTS PRIOR TO THE ISSUE OF A CONSTRUCTION CERTIFICATE

5.         Building Code of Australia

Detailed plans, specifications and supporting information is required to be submitted to the certifying authority detailing how the proposed building work achieves compliance with the National Construction Code - Building Code of Australia. All building work must be carried out in accordance with the requirements of the National Construction Code - Building Code of Australia.

6.         Contract of Insurance (Residential Building Work)

Where residential building work for which the Home Building Act 1989 requires there to be a contract of insurance in force in accordance with Part 6 of that Act, this contract of insurance must be in force before any building work authorised to be carried out by the consent commences.

7.         Notification of Home Building Act 1989 Requirements

Residential building work within the meaning of the Home Building Act 1989 must not be carried out unless the principal certifying authority for the development to which the work relates (not being Council) has given Council written notice of the following information:

a)         In the case of work for which a principal contractor is required to be appointed:

i)          The name and licence number of the principal contractor.

ii)          The name of the insurer by which the work is insured under Part 6 of that Act.

b)         In the case of work to be done by an owner-builder:

i)          The name of the owner-builder.

ii)          If the owner-builder is required to hold an owner-builder’s permit under that Act, the number of the owner-builder’s permit.

Note:  If arrangements for doing the residential building work are changed while the work is in progress so that the information notified becomes out of date, further work must not be carried out unless the principal certifying authority for the development to which the work relates (not being Council) has given Council written notification of the updated information.

8.         Utility Services

The applicant must submit written evidence of the following service provider requirements:

a)         Ausgrid (formerly Energy Australia) - a letter of consent demonstrating that satisfactory arrangements have been made to service the proposed development.

b)         Telstra/NBN - a letter of consent demonstrating that satisfactory arrangements have been made to service the proposed development.

9.         Sydney Water - Approval

This application must be submitted to Sydney Water for approval to determine whether the development would affect any Sydney Water infrastructure, and whether further requirements are to be met.

Note:  Building plan approvals can be obtained online via Sydney Water Tap inTM through www.sydneywater.com.au under the Building and Development tab.

10.        Dilapidation Report

a)         Prior to the commencement of any works on site, the applicant must submit for approval by the Principal Certifying Authority (with a copy forwarded to Council) a ‘Dilapidation Report’ detailing the structural condition of the adjoining properties:

i)          10 Edgeworth David Avenue (SP 30399)

b)         The report must include a photographic survey of the adjoining properties detailing their physical condition, both internally and externally, including such items as walls, ceilings, roof, structural members and other similar items. The report must be completed by a chartered structural/geotechnical engineer.  A copy of the dilapidation report must be submitted to Council.

c)         In the event access to adjoining allotments for the completion of a dilapidation survey is denied, the applicant must demonstrate in writing that all reasonable steps have been taken to advise the adjoining allotment owners of the benefit of this survey and details of failure to gain consent for access to the satisfaction of the Principle Certifying Authority.

Note: This documentation is for record keeping purposes only and can be made available to an applicant or affected property owner should it be requested to resolve any dispute over damage to adjoining properties arising from works. It is in the applicant’s and adjoining owner’s interest for it to be as detailed as possible

11.        Fire Safety Schedule

A schedule of all proposed essential fire safety measures to be installed in the building (e.g. hydrants, hose reels, emergency warning systems etc.) shall be submitted with the construction certificate application.

12.        Identification of Survey Marks

A registered surveyor must identify all survey marks in the vicinity of the proposed development.  Any survey marks required to be removed or displaced as a result of the proposed development shall be undertaken by a registered surveyor in accordance with Section 24 (1) of the Surveying and Spatial Information Act 2002 and following the Surveyor General’s Directions No.11 Preservation of Survey Infrastructure. 

13.        Stormwater

The stormwater drainage system for the development must be designed for an average recurrence interval (ARI) of 20 years and be gravity drained in accordance with the following requirements:

a)         Connected directly to Council’s drainage system/ street gutter.

b)         Discharge to Council gutter must be limited to 50 litres per second at any point. For more than 1 discharge point, separation is to be minimum 1m. 

c)         Be designed by a Chartered Professional Civil/ Hydraulic Engineer of the Institution of Engineers, Australia.

14.        On Site Stormwater Detention

An on-site stormwater detention system must be designed by a chartered civil engineer and constructed in accordance with the following requirements:

a)         Storage capacity to accommodate volume from up to 50 years ARI (average recurrence interval) storms and a maximum discharge (when full) limited to 5 years pre development rate.

b)         Have a surcharge/inspection grate located directly above the outlet. Discharge from the detention system to be controlled via 1 metre length of pipe, not less than 50 millimetres diameter or via a stainless plate with sharply drilled orifice bolted over the face of the outlet discharging into a larger diameter pipe capable of carrying the design flow to an approved Council system.

c)         Where above ground system is proposed and the average depth is greater than 0.3 metres, a ‘pool type’ safety fence and warning signs to be installed.

d)         Not be constructed in a location that would impact upon the visual or recreational amenity of residents.

e)         Detail calculations are to be shown in construction certificate plan.

f)          An overflow/escape path shall be incorporated in the design.

15.        Water Quality/Bio Retention System

a)         A Water Sensitive Urban Design is to be done and constructed. The stormwater leaving the premises must achieve the quality as specified in Council’s Development Control Plan 2012 (table 1C.1.2(b) Urban Stormwater Quality Targets) or utilise one of the deemed to comply solutions.   The design shall be based on Hornsby Council parameters as contained in the MUSIC Model. The design is to be carried out by a Chartered Professional Civil/ Hydraulic Engineer of the institution of Engineers, Australia.

b)         Prior to occupation of the premises, a Chartered Civil/Hydraulic Engineer of the Institution of Engineers, Australia is to certify that works have been completed in accordance with the approved construction plan and the design will achieve the targets specified in the condition.

16.        Internal Driveway/Vehicular Areas

The driveway and parking areas on site must be designed, constructed and a Construction Certificate issued in accordance with Australian Standards 2890.1, 2890.2, 3727 and the following requirements:

a)         Design levels at the front boundary shall be obtained from Council if a private accredited certifier is engaged to obtain a construction certificate for these works.

b)         The driveway be a rigid pavement.

c)         Conduit for utility services including electricity, water, gas and telephone be provided. All existing overhead assets including electricity and telecommunications cabling shall be relocated underground at no cost to Council.  A certificate from an appropriately licensed contractor shall be submitted to the principal certifying authority certifying that the service conduits have been installed in accordance with the relevant utility provider and Australian Standards.

d)         Longitudinal sections along both sides of the access driveway shall be submitted to the principal certifying authority in accordance with the relevant sections of AS 2890.1.  The maximum grade shall not exceed 1 in 4 (25%) with the maximum changes of grade of 1 in 8 (12.5%) for summit grades and 1 in 6.7 (15%) for sag grades.  Any transition grades shall have a minimum length of 2 metres.  The longitudinal sections shall incorporate the design levels obtained by Council.

17.        Road Works

All road works approved under this consent must be designed in accordance with Council’s AUS-SPEC Specifications (www.hornsby.nsw.gov.au/property/build/aus-spec-terms-and-conditions) and the following requirements:

a)         Replace the existing Kerb and gutter and footpath in front of the development site along Edgeworth David Road.

b)         Kerb and gutter along Pacific Highway frontage shall be replaced in accordance with RMS’s requirements.

c)         Existing footpath along Pacific Highway shall be replaced.

d)         No work is to commence within the road reserve until approval under Section 138 of the Roads Act 1993 is obtained from Hornsby Shire Council. In this regard a construction certificate application is to be submitted to Council.

18.        Construction Management Plan (CMP)

To assist in the protection of the public, the environment and Council’s assets, a separate Construction Management Plan must be prepared by a suitably qualified environmental consultant in consultation with Transport for New South Wales, a qualified traffic engineer and AQF 5 arborist and submitted to Council via Council’s Online Services Portal for review and written approval. 

The CMP must include the following details:

a)         A Construction Traffic Management Plan (CTMP) including the following:

i)          The order of construction works and arrangement of all construction machines and vehicles being used during all stages.

ii)          The CTMP plans shall be in accordance with all other plans submitted to Council as part of this development proposal. 

iii)         A statement confirming that no building materials, work sheds, vehicles, machines or the like shall be allowed to remain in the road reserve area without the written consent of Hornsby Shire Council.

iv)         The Plan shall be in compliance with the requirements of the Roads and Maritime Services Traffic control at work sites Manual 2018 and detail:

a.         Public notification of proposed works.

b.         Long term signage requirements.

c.         Short term (during actual works) signage.

d.         Vehicle Movement Plans, where applicable.

e.         Traffic Management Plans.

f.          Pedestrian and Cyclist access and safety.

v)         Traffic controls including those used during non-working hours. Pedestrian access and two-way traffic in the public road must be able to be facilitated at all times.

vi)         Details of parking arrangements for all employees and contractors, including layover areas for large trucks during all stages of works. The parking or stopping of truck and dog vehicles associated with the development will not be permitted other than on the site and the plan must demonstrate this will be achieved.

vii)        Confirmation that a street ‘scrub and dry’ service will be in operation during all stages of works.

viii)       Proposed truck routes to and from the site including details of the frequency of truck movements for all stages of the development.

ix)         Swept path analysis for ingress and egress of the site for all stages of works.

x)         Site plans for all stages of works including the location of site sheds, concrete pump and crane locations, unloading and loading areas, waste and storage areas, existing survey marks, vehicle entry, surrounding pedestrian footpaths and hoarding (fencing) locations.

xi)         The total quantity and size of trucks for all importation and exportation of fill on site throughout all stages of works, and a breakdown of total quantities of trucks for each stage of works.

xii)        The number of weeks trucks will be accessing and leaving the site with excavated or imported fill material.

xiii)       The maximum number of trucks travelling to and from the site on any given day for each stage of works.

xiv)       The maximum number of truck movements on any given day during peak commuting periods for all stages of works.

xv)        The source site location of any proposed fill to be imported to the site, for all stages of works.

xvi)       The Plan must state that the applicant and all employees of contractors on the site must obey any direction or notice from the Prescribed Certifying Authority or Hornsby Shire Council in order to ensure the above.

xvii)      If there is a requirement to obtain a Work Zone, Out of Hours permit, partial Road Closure or Crane Permit, the Plan must detail these requirements and include a statement that an application to Hornsby Shire Council will be made to obtain such a permit.

b)         A Construction Waste Management Plan detailing the following:

i)          Details of the importation or excavation of soil and fill, the classification of the fill, disposal methods and authorised disposal depots that will be used for the fill.

ii)          Asbestos management requirement and procedures for removal and disposal from the site in accordance with AS 2601-2001 Demolition of structures, and the Protection of the Environment Operations (Waste) Regulation 2005.

iii)         General construction waste details including construction waste skip bin locations and litter management for workers.

c)         A Tree Protection Plan (TPP) prepared by an AQF 5 Arborist in accordance with any approved Arboricultural Impact Assessment and tree location plans, detailing the following:

i)          A site plan showing tree protection zones (TPZ) and structural root zones (SRZ) of trees to be retained and specific details of tree protection measures inclusive of distances (in metres) measured from tree trunks.

ii)          Construction methodology to avoid damage to trees proposed to be retained during construction works.

iii)         Specifications on tree protection materials used and methods within the TPZ or SRZ.

iv)         Location of dedicated material storage space on site outside of TPZ’s and SRZ’s for retained trees.

d)         A Construction Noise and Vibration Management Plan (CNMP) which includes:

i)          Existing noise and vibration levels within the proximity of the proposed development site.

ii)          Details of the extent of rock breaking or rock sawing works forming part of the proposed development works.

iii)         The maximum level of noise and vibration predicted to be emitted during each stage of construction.

iv)         The duration of each stage of works where the maximum level of noise and vibration are predicted to be emitted for.

v)         Details of mitigation measures, inclusive of respite periods, that will meet acoustic standards and guidelines at each stage of works.

vi)         Details of a complaints handling process for the surrounding neighbourhood for each stage of works.

e)         Identification of approved sediment and erosion control measures.

f)          The CMP must detail the contact information for developers, builder, private certifier and any emergency details during and outside work hours.

Note:  The CMP must be lodged via Council’s Online Services Portal at: https://hornsbyprd-pwy-epw.cloud.infor.com/ePathway/Production/Web/Default.aspx and by selecting the following menu options: Applications > New Applications > Under ‘Application Types’: Management Plans.

19.        Environmental Management Plan (EMP)

An Environmental Management Plan (EMP) is to be submitted to Council’s Compliance Team via Council’s Online Services Portal for review and written approval, prior to the issue of a Construction Certificate. The EMP is to be prepared by a suitably qualified Environmental Consultant detailing the actions that will be taken to protect the environment for the duration of works, and all responsible parties ensuring compliance with the document. The Plan is to be in accordance with the publication ‘Managing Urban Stormwater - Landcom (March 2004)’, the Protection of the Environment Operations Act 1997 and relevant Council guidelines, and should include but not be limited to:

a)         Water quality and soil management, including but not limited to sediment and erosion control measures and stormwater management.

b)         Air quality.

c)         Noise management, including excavation noise mitigation measures to be implemented.

d)         Waste Management.

e)         Tree Protection Management inclusive of tree protection measures.

f)          Unexpected finds protocol to manage contamination finds.

Note:  The EMP must be lodged via Council’s Online Services Portal at: https://hornsbyprd-pwy-epw.cloud.infor.com/ePathway/Production/Web/Default.aspx and by selecting the following menu options: Applications > New Applications > Under ‘Application Types’: Management Plans.

20.        Noise - Rail Corridor

a)         Prior to the issue of a Construction Certificate, an Acoustic Report prepared by a suitably qualified environmental consultant in accordance with the requirements of the Department of Planning’s Development Near Rail Corridors and Busy Roads - Interim Guideline and RailCorp’s Interim Guidelines for Applicants must be submitted to the Principal Certifying Authority. The Acoustic Report must demonstrate that appropriate measures will be taken to ensure that the following LAeq levels are not exceeded:

i)          In any bedroom in the residential accommodation - 35dB(A) at any time between 10:00pm and 7:00am, and

ii)          Anywhere else in the residential accommodation (other than a garage, kitchen bathroom or hallway) - 40dB(A) at any time.

b)         The development must be carried out in accordance with the recommendations contained within the Acoustic Report submitted with the Construction Certificate application.

Note:  The Department of Planning’s document is available at www.planning.nsw.gov.au (development assessments). 

Note:  The RailCorp document is available at www.railcorp.nsw.gov.au/publications.

21.        Waste Management Details

The following waste management requirements must be complied with:

a)         No steps/ bin and waste carting routes

i)          There must be no steps along any bin carting route. Ramps and service lifts are acceptable.

  Note: bin carting routes include, but are not limited to, from the bin storage rooms to the ground level temporary bin holding bay, from the ground level bin storage/holding bay to the kerbside.

ii)          For all bin carting routes, the path must be smooth hard surface. (Concrete pavement for example is acceptable, but pebbles, stepping stones, grass etc is not acceptable).

iii)         A design certificate and detailed plans are to accompany any Construction Certificate application, which demonstrate that the bin carting route from the ground level bin temporary bin holding bay to the parked waste collection vehicle has been designed to be constructed in accordance with the Waste Minimisation and Management Guidelines and including the following requirements:

a.         Must be smooth hard surface.

b.         Must be sufficiently wide to hold all serviceable bins and provide aisle space for manoeuvring bins out and in (including through any gates or doors).

c.         Must be devoid of steps.

d.         Must have a gradient no steeper than 1:14 for 240L bins and 1:20 for 660L or 1100L bins.

iv)         A design certificate and detailed plans are to accompany any Construction Certificate application, which demonstrate that the waste carting route from each dwelling to the bulky waste storage area has been designed to be constructed in accordance with the Waste Minimisation and Management Guidelines and including the following requirements:

a.         The route is direct, does not cross into a private lot, and is wholly within property boundaries (does not include the public footpath or road).

b.         The route is as short as possible and does not exceed 30m walking distance.

c.         The route is an accessible path of travel for persons with a disability in accordance with AS1428 Design and Access for Mobility.

b)         Bin storage rooms at ground level

i)          A design certificate and detailed plans are to accompany any Construction Certificate application, which demonstrate that all waste storage room(s) at ground level have been designed to be constructed in accordance with the Waste Minimisation and Management Guidelines and including the following requirements:

a.         The floor is to be constructed of concrete at least 75mm thick and adequately graded to drain to a Sydney Water approved drainage fitting.

b.         The floor must be finished so that it is non-slip, sealed and impervious, and has a smooth and even surface coved at all intersections.

c.         The ceilings and walls must be finished with smooth faced non-absorbent material capable of being cleaned.

d.         The room is to be provided with artificial light controllable within the room and adequate forced ventilation.

e.         The room is to be provided with an adequate supply of hot and cold water mixed through a centralised mixing valve with hose cock.

f.          The doors are to be robust and lockable, with door openings suitable for manoeuvring the required bins through. The doors must be able to be opened from inside the room without a key.

g.         The doors to the bin rooms must be wide enough to fit a 1100L bin through ,double doors should be provided.

ii)          If the 240L bins are to be decanted into 1100L bins at ground level, provision needs to be made for a bin lifter.

c)         Waste facilities in FACF dirty utility rooms

i)          The dirty utility rooms on each level must include space for a garbage and recycling bin.

ii)          must be a waste facility (a garbage chute, plus 1 x 240L recycling bin & 1 x 240L future FOGO bin in a cupboard or small room) on each residential level of each lift core of each building. Each waste facility must:

a.         Be accessible by persons with a disability after the garbage chute, recycling bin and FOGO bin are installed.

b.         Comfortably house the required garbage chute and 240 L recycling bin and 240L FOGO bin.

c.         Have door(s) wide enough and positioned so that the 240 L recycling bin and 240L FOGO bin can fit through with ease.

Note: 240L bins are 600mm wide, 750mm deep, 1100mm high. To allow for ease around the bin an additional 75mm is recommended. These dimensions do not include wall thickness, door thickness, ventilation ducting etc, which must be added. The chute system supplier must be consulted for chute space requirements. AS1428.1 requires at least 800mm clear doorway opening for wheelchair access.

REQUIREMENTS PRIOR TO THE COMMENCEMENT OF ANY WORKS

22.        Erection of Construction Sign

a)         A sign must be erected in a prominent position on any site on which any approved work is being carried out:

i)          Showing the name, address and telephone number of the principal certifying authority for the work.

ii)          Showing the name of the principal contractor (if any) for any demolition or building work and a telephone number on which that person may be contacted outside working hours.

iii)         Stating that unauthorised entry to the work site is prohibited.

b)         The sign is to be maintained while the approved work is being carried out and must be removed when the work has been completed.

23.        Protection of Adjoining Areas

A temporary hoarding, fence or awning must be erected between the work site and adjoining lands before the works begin and must be kept in place until after the completion of the works if the works:

a)         Could cause a danger, obstruction or inconvenience to pedestrian or vehicular traffic.

b)         Could cause damage to adjoining lands by falling objects.

c)         Involve the enclosure of a public place or part of a public place.

d)         Have been identified as requiring a temporary hoarding, fence or awning within the Council approved Construction Management Plan (CMP).

Note:  Notwithstanding the above, Council’s separate written approval is required prior to the erection of any structure or other obstruction on public land.

24.        Toilet Facilities

a)         To provide a safe and hygienic workplace, toilet facilities must be available or be installed at the works site before works begin and must be maintained until the works are completed at a ratio of one toilet for every 20 persons employed at the site.

b)         Each toilet must:

i)          Be a standard flushing toilet connected to a public sewer.

ii)          Be a temporary chemical closet approved under the Local Government Act 1993.

iii)         Have an on-site effluent disposal system approved under the Local Government Act 1993.

25.        Erosion and Sediment Control

To protect the water quality of the downstream environment, erosion and sediment control measures must be provided and maintained throughout the construction period in accordance with the manual ‘Soils and Construction 2004 (Bluebook)’, the approved plans, Council specifications and to the satisfaction of the principal certifying authority.  The erosion and sediment control devices must remain in place until the site has been stabilised and revegetated.

Note:  On the spot penalties may be issued for any non-compliance with this requirement without any further notification or warning.

26.        Garbage receptacle

a)         A garbage receptacle must be provided at the work site before works begin and must be maintained until all works are completed.

b)         The garbage receptacle must have a tight fitting lid and be suitable for the reception of food scraps and papers.

c)         The receptacle lid must be kept closed at all times, other than when garbage is being deposited.

d)         Food scraps must be placed in the garbage receptacle and not in demolition and construction waste bins.

REQUIREMENTS DURING CONSTRUCTION

27.        Construction Work Hours

All work on site (including demolition and earth works) must only occur between 7am and 5pm Monday to Saturday (unless otherwise approved in writing by Council due to extenuating circumstances). No work is to be undertaken on Sundays or public holidays.

28.        Environmental Management

To prevent sediment run-off, excessive dust, noise or odour emanating from the site during the construction, the site must be managed in accordance with the publication ‘Managing Urban Stormwater - Landcom (March 2004) and the Protection of the Environment Operations Act 1997.

29.        Street Sweeping

During works and until exposed ground surfaces across the site have been stabilised, street sweeping must be undertaken following sediment tracking from the site.

The street cleaning service must utilise a ‘scrub and dry’ method and be undertaken for the full extent of any sediment tracking. 

30.        Compliance with Environmental Management Plan (EMP)

The Council approved Environmental Management Plan must be complied with for the duration of works, unless otherwise approved by Council.

31.        Council Property

To ensure that the public reserve is kept in a clean, tidy and safe condition during construction works, no building materials, waste, machinery or related matter is to be stored on the road or footpath. 

32.        Disturbance of Existing Site

During construction works, the existing ground levels of open space areas and natural landscape features, including natural rock-outcrops, vegetation, soil and watercourses must not be altered unless otherwise nominated on the approved plans.

33.        Landfill not Permitted

The importation of fill material associated with earthworks, or structural or engineering works, is not permitted as part of this consent.

34.        Excavated Material

All excavated material removed from the site must be classified by a suitably qualified environmental consultant in accordance with the NSW Environment Protection Authority’s Waste Classification Guidelines and Protection of the Environment Operations (Waste) Regulation 2014 prior to disposal to a licensed waste management facility.   Tipping dockets for the total volume of excavated material that are received from the licensed waste management facility must be provided to the principal certifying authority prior to the issue of an Occupation Certificate.

35.        Maintenance of public footpaths

Public footpaths must be maintained for the duration of works to ensure they are free of trip hazards, displacements, breaks or debris to enable pedestrians to travel along the footpath safely.

36.        Compliance with Construction Management Plan

The Council approved Construction Management Plan must be complied with for the duration of works, unless otherwise approved by Council.

37.        Building Materials and Site Waste

The stockpiling of building materials, the parking of vehicles or plant, the disposal of cement slurry, waste water or other contaminants must be located outside the tree protection zones as prescribed in the conditions of this consent of any tree to be retained.

38.        Unexpected Finds

Should the presence of asbestos or soil contamination, not recognised during the application process be identified during any stage of works, the applicant must immediately notify the PCA and Council.

39.        Waste Management Details

Requirements of the approved Waste Management Plan shall be complied with during all site preparation works, demolition and throughout all construction works. When implementing the Waste Management Plan, the developer is to ensure:

a)         The disposal of any demolition and construction waste must be undertaken in accordance with the requirements of the Protection of Environment Operations Act 1997

b)         All waste on site is to be stored, handled and disposed of in such a manner as to not create air pollution, offensive noise or pollution of land and water as defined by the Protection of Environment Operations Act 1997

c)         Generation, storage, treatment and disposal of hazardous waste is conducted in accordance with the relevant waste legislation administered by the EPA and relevant Occupational Health and Safety legislation administered by WorkCover NSW

d)         All waste generated (including excavated materials) which cannot be reused or recycled must be transported to a facility which can lawfully accept it

e)         All materials and resources that are to be stored on site during construction works are contained on the site. The provisions of the Protection of Environment Operations Act 1997 must be complied with when placing/stock piling loose material, disposal of concrete waste or activities which have potential to pollute drains and water courses

f)          The storage of waste and recycling containers must be within the boundaries of the development site at all times. Public footways and roads must not be used for the storage of any waste and must be kept clear of obstructions during all construction works

g)         Additionally, written records of the following items must be maintained during the removal of any waste from the site and such information submitted to the Principal Certifying Authority within fourteen days of the date of completion of the works:

i)          The identity of the person removing the waste.

ii)          The waste carrier vehicle registration.

iii)         Date and time of waste collection.

iv)         A description of the waste (type of waste and estimated quantity).

v)         Details of the site to which the waste is to be taken.

vi)         The corresponding weighbridge tip docket/receipt from the site to which the waste is transferred (noting date and time of delivery, description (type and quantity) of waste).

vii)        Whether the waste is expected to be reused, recycled or go to landfill.

    Note: In accordance with the Protection of the Environment Operations Act 1997, the definition of waste includes any unwanted substance, regardless of whether it is reused, recycled or disposed to landfill.

h)         A report(s) must be prepared by a registered surveyor and submitted to the principal certifying authority:

i)          Prior to the pouring of the concrete on the ground level, certifying that: the ground level bin storage/holding bay rooms are at the same level as the driveway (no steps).

40.        Vehicular Crossing

A separate application under the Local Government Act 1993 and the Roads Act 1993 must be submitted to Council for the installation of a new vehicular crossing and the removal of the redundant crossing.  The vehicular crossing must be constructed in accordance with Council’s AUS-SPEC Specifications.

(www.hornsby.nsw.gov.au/property/build/aus-spec-terms-and-conditions)

and the following requirements:

a)         Design levels at the front boundary must be obtained from Council for the design on the internal driveway.

b)         Any redundant crossings must be replaced with integral kerb and gutter.

c)         The footway area must be restored by turfing.

d)         Approval must be obtained from all relevant utility providers that all necessary conduits be provided and protected under the crossing.

Note:  An application for a vehicular crossing can only be made to one of Council’s Authorised Vehicular Crossing Contractors.  You are advised to contact Council on 02 9847 6940 to obtain a list of contractors.

41.        Survey Report

A report(s) must be prepared by a registered surveyor and submitted to the principal certifying authority:

a)         Prior to the pouring of concrete at each level of the building certifying that:

ii)          The building, retaining walls and the like have been correctly positioned on the site.

iii)         The finished floor level(s) are in accordance with the approved plans.

REQUIREMENTS PRIOR TO THE ISSUE OF AN OCCUPATION CERTIFICATE

42.        Damage to Council Assets

To protect public property and infrastructure, any damage caused to Council’s assets as a result of the construction or demolition of the development must be rectified by the applicant in accordance with AUS-SPEC Specifications.

(www.hornsby.nsw.gov.au/property/build/aus-spec-terms-and-conditions)

 Rectification works must be undertaken prior to the issue of an Occupation Certificate, or sooner, as directed by Council.

43.        Streetscape paving

a)         Streetscape pavement works are to be provided within the Edgeworth David Avenue and Pacific Highway road verge.

b)         Paving works are to include a fully paved verge using Claypave ‘Monarch Tan’ 230 x 110 x 60mm unit paving laid in a 45degree herringbone pattern with header course.

c)         Pavers are to be laid on bedding sand over a 100mm thick concrete base slab. A 90 degree Header is to be provide around all the paving areas including to the tree planter pits.

44.        Street Tree Plantings

a)         Street tree plantings along the frontage to Edgeworth David Avenue shall include:

i)          Street tree planting is to consist of three (3) Leptospermum conferta (Brushbox) planted at a minimum pot size of 75 litres.

b)         Street tree plantings along the frontage to Pacific highway should include:

i)          Street tree planting is to consist of two (2) Corymbia maculata (spotted gum) planted at a minimum pot size of 75 litres.

c)         Trees are to be placed in sufficient soil area and have the following specifications:

i)          Be 2m x 4m x 0.5m deep per tree creating a minimum volume of structural soils of 4m3 per tree. Imported tree pit soil is to be structural soils such as 40mm aggregate free draining granular material similar to that provided by Benedicts Pty Ltd to create an adequate lateral growing volume below the pavement.

ii)          Tree pit areas are to have surface area opening of 2m x 1m with the finished surface mulch in the tree pit to be compacted decomposed granite similar to that supplied by ANL Pty Ltd. 50mm thick.

Note: Applicants are advised to pre-order plant material required in pot sizes 45 litre or larger to ensure Nurseries have stock available at the time of install.

45.        Planter Pots

Planter Pots must include automatic irrigation, sufficient soil depth and adequate drainage to ensure sustainable landscape is achieved.

46.        Completion of Landscaping

A certificate must be provided by a practicing landscape architect, horticulturalist or person with similar qualifications and experience certifying that all required landscaping works have been satisfactorily completed in accordance with the approved landscape plans.

47.        Asbestos Clearance Certificate

Should any asbestos be encountered during demolition or construction works, a licenced asbestos assessor is required to provide a Clearance Certificate to the Certifier prior to the issue of an Occupation Certificate, certifying that the asbestos has been removed and appropriately disposed of, and the site is now suitable for its approved use. 

48.        Works as Executed Plan

A works-as-executed plan(s) must be prepared by a registered surveyor and submitted to Council for completed diversion of Council pipe, overland flow path, footpath, driveway, on-site detention and water sensitive urban design systems. The plan(s) must be accompanied by a certificate from a registered surveyor certifying that all pipelines and associated structures lie wholly within any relevant easements.

49.        Creation of Easements

The following matter(s) must be nominated on the plan of subdivision under s88B of the Conveyancing Act 1919

a)         The creation of an appropriate "Positive Covenant" and "Restriction as to User" over the constructed on-site detention and water sensitive urban design systems/ rain water tanks and outlet works, within the lots in favour of Council in accordance with Council’s prescribed wording.  The positions of the on-site detention system and water sensitive urban design systems/ rainwater are to be clearly indicated on the title.

b)         To register the positive covenant and the restriction on the use of land, “works-as-executed” details of the on-site-detention and water sensitive urban design systems must be submitted verifying that the required storage and discharge pipes of the on- site detention system and the water sensitive urban system/ rain water tank  have been constructed in accordance with the design requirements.  The details must show the invert levels of pipes, pipe sizes and grades and filters/bio retention basin. Any variations to the approved plans must be shown in red on the “works-as-executed” plan and supported by calculations

50.        Preservation of Survey Infrastructure

Prior to the issue of a construction certificate, a registered surveyor shall identify all survey marks in the vicinity of the proposed development.  Any survey marks required to be removed or displaced as a result of the proposed development shall be undertaken by a registered surveyor in accordance with Section 24 (1) of the Surveying and Spatial Information Act 2002 and following the Surveyor General’s Directions No.11 - Preservation of Survey Infrastructure. 

51.        Completion of Works and Compliance Certificate

All engineering works identified in this consent are to be completed and a Compliance Certificate issued prior to the release of occupation permit.

52.        Fire Safety Statement - Final

In accordance with the Environmental Planning and Assessment (Development Certification and Fire Safety) Regulation 2021, upon completion of the building, the owner must provide Council with a certificate in relation to each fire safety measure implemented in the building.

53.        Submission of Excavated Material Tipping Dockets to Principal Certifying Authority

Tipping dockets for the total volume of excavated material that are received from the licensed waste facility must be provided to the Principal Certifying Authority prior to the issue of an Occupation Certificate.

54.        Traffic Signage

A ‘left turn into the kerb side lane only’ sign is to be installed within the boundary of the property facing exit side of the driveway.

55.        Provision for National Broadband Network (NBN)

Provision must be made for fibre ready passive infrastructure (pits and pipes) generally in accordance with NBN Co's pit and pipe installation guidelines to service the proposed development. A certificate from NBN Co or Telstra must be submitted to the PCA that the fibre optic cabling provided for the development complies with MDU Building Design Guides for Development.

56.        External Lighting

a)         To protect the amenity of adjacent premises, all external lighting must be designed and installed in accordance with Australian Standard AS4282 Control of the obtrusive effects of outdoor lighting. 

b)         Certification of compliance with this Standard must be obtained from a suitably qualified person and submitted to the PCA with the application for the Occupation Certificate.

57.        Retaining Walls

All retaining walls must be constructed as part of the development and prior to the issue of an Occupation Certificate.

58.        Waste Management Details

The following waste management requirements must be complied with:

a)         Prior to an Occupation Certificate being issued or the use commencing, whichever is earlier, the Principal Certifying Authority must obtain Council’s approval of the waste and recycling management facilities provided in the development and ensure arrangements are in place for domestic waste collection by Council.

Note: Waste and recycling management facilities includes everything required for on-going waste management on the site. For example the bin storage areas, bulky waste storage area, bin collection area, waste collection vehicle access, doors wide enough to fit the bin through, accessibility, bin carting routes etc.

b)         Prior to an Occupation Certificate being issued or the use commencing, whichever is earlier, all external works including but not limited to the vehicular crossover and footpath, must be completed. For staged occupation (where the Occupation Certificate will be limited to a portion of the development):

i)          Prior to the issue of the occupation certificate or the use commencing, whichever is earlier, for each stage of the development the waste management system (including but not limited to the bin storage room, bin holding bay, the road/accessway and vehicular crossover, loading bay and truck turning area) for that stage, must be completed.

c)         A report must be prepared by an appropriately qualified person, certifying the following:

i)          A comparison of the estimated quantities of each demolition and construction waste type against the actual quantities of each waste type.

Note: Explanations of any deviations to the approved Waste Management Plan is required to be included in this report

ii)          That at least 60% of the waste generated during the demolition and construction phase of the development was reused or recycled.

Note: If the 60% diversion from landfill cannot be achieved in the Construction Stage, the Report is to include the reasons why this occurred and certify that appropriate work practices were employed to implement the approved Waste Management Plan. The Report must be based on documentary evidence such as tipping dockets/receipts from recycling depots, transfer stations and landfills, audits of procedures etc. which are to be attached to the report.

iii)         All demolition and construction waste was taken to site(s) that were lawfully permitted to accept that waste.

d)         The bin carting routes must be devoid of any steps and must be wholly within the site.

Note: Ramps between different levels are acceptable. The use of the public footpath is not acceptable.

e)         All lockable doors and gates, both pedestrian and vehicular, that are required to be opened by Council’s waste collection contractor in the provision of waste collection services, must be able to be opened using a pin code. That is, locks requiring keys, remote controls, key fobs etc are not acceptable.

f)          The bin storage rooms at the ground level must comfortably house all of the bins required to be stored there.

g)         The temporary bin holding bay at the ground level must include sealed and impervious surfaces, robust door(s), adequate lighting and ventilation, and must be lockable. The walls must be finished with smooth faced non-absorbent material capable of being cleaned. The temporary bin holding bay must include water or a hose for cleaning, and graded floors draining to sewer.

59.        Garbage Collection Easement

For the purpose of waste collection, an easement entitling Council, its servants and agents and persons authorised by it to enter upon the subject land and to operate thereon, vehicles and other equipment for the purposes of waste collection must be granted to Council by the owner of the land.  The waste collection easement must be registered with the NSW Land Registry Services prior to issue of the occupation certificate.

Note:  The easement must be in a form prescribed by Council and must include covenants to the effect that parties will not be liable for any damage caused to the subject land or any part thereof or to any property located therein or thereon by reason of the operation thereon of any vehicle or other equipment used in connection with the collection of garbage and to the effect that the owner for the time being of the subject land shall indemnify the Council, its servants, agents and persons authorised by it to collect garbage against liability in respect of any such claims made by any person whomsoever.

60.        Restriction on Occupation - Housing for Seniors or People with a Disability

A restriction as to user must be created under s88E of the Conveyancing Act 1919 and registered, requiring all residential dwellings approved under this consent to be solely used for the accommodation of:

a)         Seniors (55+ age) or people who have a disability.

b)         People who live within the same household as seniors or people with a disability.

c)         Staff employed to assist the administration and provision of services to housing provided under State Environmental Planning Policy (Housing) 2021.

Note:  The restriction must nominate Council as the authority to release, vary or modify the restriction.

OPERATIONAL CONDITIONS

61.        Hours of Operation

a)         The hours of operation of the commercial tenancies are restricted to those times listed below unless otherwise approved in writing by Council:

Monday to Saturday          7 am to 6 pm

Sunday & Public Holidays 8am to 6pm

b)         All deliveries must take place within the approved hours of operation.

62.        Fire Safety Statement - Annual

On at least one occasion in every 12 month period following the date of the first ‘Fire Safety Certificate’ issued for the property, the owner must provide Council with an annual ‘Fire Safety Certificate’ certifying each essential service installed in the building.

63.        Landscape establishment

The landscape works must be maintained into the future to ensure the establishment and successful growth of plant material to meet the intent of the landscape design. This must include but not be limited to watering, weeding, replacement of failed plant material and promoting the growth of plants through standard industry practices.

64.        Noise - Operational

a)         All noise generated by the proposed development must be attenuated to prevent levels of noise being emitted to adjacent premises which possess tonal, beating and similar characteristics or which exceeds background noise levels by more than 5dB(A).

b)         An acoustic assessment is to be undertaken by a suitably qualified environmental consultant within 60 days of occupying the site in accordance with the Environment Protection Authority’s Noise Policy for Industry (2017), Council’s Policy and Guidelines for Noise and Vibration Generating Development (Acoustic Guidelines V.5, 2000) and the DECC’s Noise Guide for Local Government (2004).  The assessment must be held on site for review by Council if necessary.  Should the assessment find that noise from the premises exceeds 5dB(A) above background noise levels, appropriate measures must be employed to rectify excessive noise.

65.        Waste Management

The waste management on site must be in accordance with the following requirements:

a)         The approved Waste Management Plan is to be implemented throughout the ongoing use of the development.

b)         There must be a sufficient number of bins on site to contain the volume of waste and recycling expected to be generated between collection services. There must be a sufficient number of rotational bins on site for there to be a garbage bin under each chute and a recycling bin in each bin cupboard on each residential level on collection days.

c)         A site caretaker must be employed and be responsible for:

i)          Moving bins where and when necessary, washing bins and maintaining waste storage areas and signage, ensuring the chute systems and related devices are regularly checked and maintained in effective and efficient working order. Maintaining and checking all waste management equipment (e.g. bin cart/tug), managing the bulky item storage area, arranging the prompt removal of dumped rubbish, arranging for shopping trolleys to be promptly returned to the local shopping centre(s), ensuring recycling bins are free of contamination (which includes but is not limited to garbage, plastic bags, clothing, etc.), addressing overflowing bins and pest infestations, liaising with Council on waste matters and ensuring all residents are informed and kept up to date on the use of the waste management system. The site caretaker must be employed for a sufficient number of hours each week to allow all waste management responsibilities to be carried out to a satisfactory standard.

Note: bins are to be placed in the holding area the day before the collection day, then returned to the basement bin storage rooms promptly after servicing.

d)         No waste storage containers are to be located or placed outside of the approved waste storage area at any time except for collection purposes.

e)         Adequate signage is to be provided and maintained on how to use the waste management system and what materials are acceptable for recycling within all waste storage areas of the development. Signage is also to be provided and maintained which clearly identifies which bins (and containers) are to be used for general waste and recycling and what materials can be placed in each bin. Signage is also to be provided in locally appropriate culturally and linguistically diverse (CALD) community languages.

Note: Council may be able to assist with signage.

f)          Where the development incorporates strata title subdivision, the by-laws are to clearly set out the management responsibilities for the developments waste management system.

g)         Where the waste management system includes a chute system, there needs to be a contingency plan to allow for the continual disposal and collection of waste if the chute cannot be operated.

h)         All equipment required in the operation of the approved waste management system must be regularly checked and maintained in effective and efficient working order in accordance with the manufacturers instructions by trained service technicians.

66.        Car Parking

All car parking must be constructed and operated in accordance with Australian Standard AS/NZS2890.1:2004 Off-street car parking and Australian Standard AS2890.2:2002 Off-street commercial vehicle facilities.

a)         All parking areas and driveways are to be sealed to an all-weather standard, line marked and signposted.

b)         Car parking, loading and manoeuvring areas to be used solely for nominated purposes.

c)         Vehicles awaiting loading, unloading or servicing shall be parked on site and not on adjacent or nearby public roads.

d)         All vehicular entry on to the site and egress from the site shall be made in a forward direction.

e)         Visitors must be able to access the visitor parking spaces at all times.  These spaces are not to be used by residents as storage or parking spaces

f)          Motorcycle parking spaces are to be designed in accordance with Australian Standard AS/NZS2890.1:2004 Figure 2.7.

g)         Bicycle parking spaces are to be designed in accordance with Australian Standard AS2890.3-1993 Bicycle parking facilities.

CONDITIONS OF CONCURRENCE - TRANSPORT FOR NSW

The following conditions of consent are from the nominated State Agency pursuant to Section 4.13 of the Environmental Planning and Assessment Act 1979 and must be complied with to the satisfaction of that Agency.

67.        TfNSW 1

The awning is to be setback a minimum of 600mm from the face of kerb to protect the structure from vehicle overhang.

68.        TfNSW 2

The awning is not to hinder driver sight distances to the traffic signal lanterns.

69.        TfNSW 3

The developer is to submit design drawings and documents relating to the excavation of the site and support structures to TfNSW for assessment, in accordance with Technical Direction GTD2020/001.

The developer is to submit all documentation at least six (6) weeks prior to commencement of construction and is to meet the full cost of the assessment by TfNSW. Please send all documentation to development.sydney@transport.nsw.gov.au

If it is necessary to excavate below the level of the base of the footings of the adjoining roadways, the person acting on the consent shall ensure that the owner/s of the roadway is/are given at least seven (7) day notice of the intention to excavate below the base of the footings. The notice is to include complete details of the work.

70.        TfNSW 3

The proposed development, noting its use, should be designed, as per the requirements of clause 101 (2)(c) of State Environmental Planning Policy (Infrastructure) 2007 such that it includes measures to ameliorate potential traffic noise or vehicle emissions noise within the site of the development arising from the Pacific Highway. These measures shall be certified by an appropriately qualified noise and air quality expert and noted on the plans prior to issue of a Construction Certificate.

71.        TfNSW 4

All demolition and construction vehicles are to access the site via Edgeworth David Avenue. A construction zone will not be permitted on the Pacific Highway.

CONDITIONS OF CONCURRENCE - Sydney Trains

The following conditions of consent are from the nominated State Agency pursuant to Section 4.13 of the Environmental Planning and Assessment Act 1979 and must be complied with to the satisfaction of that Agency.

72.        A1

Unless amendments are required in order to obtain approval/certification/compliance from Sydney Trains in relation to any of the Sydney Trains related conditions of consent, all excavation and construction works are to be undertaken in accordance with the details, methodology, advice, undertakings, and recommendations as detailed in the following documents:

a)         Geotechnical Investigation Report prepared by Douglas Partners, reference 99895.00, revision 1, dated 19 April 2022.

b)         Civil & Structural Design Plans prepared by MAJCON Consulting:

i)          Site Retention Works Construction Notes & Drawing Index, reference 20190057-SRO, revision E, dated 10 May 2022.

ii)          Site Retention Works Ground Floor Plan Showing Shoring, reference 20190057-SR1, revision B, dated 4 March 2022.

iii)         Site Retention Works Basement-1 Floor Plan Showing Shoring, reference 20190057-SR2, revision B, dated 4 March 2022.

iv)         Site Retention Works Basement-2 Floor Plan Showing Shoring, reference 20190057-SR3, revision B, dated 4 March 2022.

v)         Site Retention Works Basement-3 Floor Plan Showing Shoring, reference 20190057-SR4, revision B, dated 4 March 2022.

vi)         Site Retention Works, Site Cross Sections & Construction Sequence, reference 20190057-SR5, revision F, dated 20 May 2022.

vii)        Site Retention Works- Cross Section Z-Z Showing Bridge Abutment, reference 20190057-SR6, revision C, dated 20 May 2022.

c)         Site Retention Design Report prepared by MAJCON Consulting, reference MAJ20190057-REP 01 REV 06 20 05 2022, revision 6, dated 20 May 2022.

d)         Detailed Survey Plans prepared by Craig & Rhodes, reference 122-02, Drawings 122-02 T06 [03] Sheet 1 of 2 & 2 of 2, revision 03, dated 11 March 2022.

e)         Architectural Plans prepared by Coble Stephens Architects (CSA), reference 610- 17-458, revision R, dated 7 February 2022:

i)          Detail Plan - Blowout 33kV Line, Sheet 40 of 47 DA-40R.

ii)          Detail Plan - Blowout 11kV Line, Sheet 41 of 47 DA-41R.

iii)         Blowout Sections - Option A - Crane/Precast Panels, Revision R, Reference 610-17-458, Sheet 42 of 47 DA-42R.

iv)         Blowout Sections - Option B - Scaffolding, Reference 610-17-458, Revision R, Sheet 43 of 47 DA-43R.

v)         Blowout Sections - Option C - Maintenance, Sheet 44 of 47 DA-44R.

vi)         Blowout/Crane Section Through Lift Shaft, Sheet 45 of 47 DA-45R.

f)          Ground Floor Plan - Retail prepared by Coble Stephens Architects (CSA), Reference 610-17-458, Revision R, Sheet 3 of 46 DA-03R, dated 16 September 2021.

g)         First Floor Plan - Commercial prepared by Coble Stephens Architects (CSA), Reference 610-17-458, Revision M, Sheet 5 of 32 DA-04L, dated 20 August 2020.

h)         Electrical Blowout Design Report prepared by ECL Power Services (No Reference) dated 30 July 2021.

i)          Electrical Blowout Plan prepared by ECL Power Services, reference Hornsby 01, Sheet 1, revision A, dated 30 July 2021.

j)          Plans prepared and certified by Craig & Rhodes, reference 122-02, dated 23 March 2022:

i)          Craneage Plan/Electrical Blowout Plans Survey, Drawing 122-02G T09 [06] - Plan 8.

ii)          Scaffolding Plan/Electrical Blowout Plans Survey, Drawing 122-02G T09 [06] - Plan 7; iii. Pre-Cast Panel/Electrical Blowout Plans Survey, Drawing 122-02G T09 [06] - Plan 6.

iii)         Detail Survey Plan/Electrical Blowout 33kV Plans Survey, Drawing 122- 02G T09 [06] - Plan 5.

iv)         Detail Survey Plan/Electrical Blowout 11kV Plans Survey, Drawing 122- 02G T09 [06] - Plan 4.

v)         Crane Cross-Sectional Plan/Electrical Blowout Plans Survey, Drawing 122-02G T09 [06] - Plan 3.

vi)         Craneage Survey Plan/Electrical Blowout Survey, Drawing 122-02G T09 [06] - Plan 2; and

vii)        Craneage Survey Plan/Electrical Blowout Plans Survey, Drawing 122-02G T09 [06] - Plan 1.

k)         TBG Senior Living Services Pty Ltd email (Signed by Matthew Blissett) dated 3 March 2022.

The Principal Certifying Authority is not to issue the Construction Certificate until written confirmation has been received from Sydney Trains confirming which of the documentation listed in this condition are to now apply or are superseded as a result of the compliance with the Sydney Trains related conditions of consent. The measures detailed in the documents approved/ certified by Sydney Trains under this Condition are to be incorporated into the construction drawings and specifications prior to the issuing of the Construction Certificate. Prior to the commencement of works the Principal Certifying Authority is to provide verification to Sydney Trains that this condition has been complied with.

73.        B1.

Prior to the issue of a Construction Certificate, the Applicant is to consult with Sydney Trains and provide details as agreed upon for unfettered access to Sydney Trains access gates and TAHE (Transport Asset Holding Entity) owned land and assets, during and postconstruction. The Applicant should ensure provision for easy and ongoing 24/7 access by rail vehicles, plant, and equipment to support maintenance and emergency activities. The Principal Certifying Authority is not to issue any Construction Certificate, until written confirmation has been received from Sydney Trains confirming this condition has been satisfied.

74.        B2.

If required, prior to the commencement of works, the Applicant shall enter into a Licence Agreement with Sydney Trains/TAHE (Transport Asset Holding Entity) for the formalisation of access to Sydney Trains access gates/TAHE (Transport Asset Holding Entity) owned land and assets.

75.        B3.

Prior to the issue of a Construction Certificate, the applicant is to consult with Sydney Trains/TAHE (Transport Asset Holding Entity), and provide documentation of registration of the Easement on Title as agreed upon for the provision of a Right of Carriageway Easement under c88B of the Conveyancing Act 1919, as part of the proposed development to allow for continued access to Sydney Trains access gates and TAHE (Transport Asset Holding Entity) owned land and assets for maintenance and emergency purposes.

76.        B4.

A Plan of Survey and associated easement terms defining the extent of the easement is required to be submitted to Sydney Trains/TAHE (Transport Asset Holding Entity) for endorsement. The location of the new easement (including easement terms) will be in accordance with Sydney Trains/TAHE (Transport Asset Holding Entity) requirements. The responsibility of creating and registering the new easement shall be the Applicant’s and at their cost. The Principal Certifying Authority is not to issue any Occupation Certificate until written confirmation has been received from Sydney Trains confirming its endorsement of the new easement (including easement terms), and confirmation that the Applicant has registered the new easement on Title.

77.        B5.

Prior to the commencement of any works, the applicant is to prepare and provide to Sydney Trains for review and endorsement a Hydrologic Assessment report demonstrating that the dewatering during construction will not have any adverse settlement impacts on the rail corridor. No works are to commence until this report has been endorsed by Sydney Trains.

78.        B6.

Prior to the commencement of any works, a Registered Surveyor shall peg-out the common property boundary between the development site and TAHE (Transport Asset Holding Entity) land and easements. A copy of the survey report indicating the location of pegs must be provided to Sydney Trains prior to the commencement of works.

79.        B7.

Prior to the issuing of a Construction Certificate, the Applicant shall prepare and provide to Sydney Trains for review, comment, and written endorsement the following final version rail specific items in compliance with Sydney Trains’ requirements and the relevant ASA Standards (https://www.transport.nsw.gov.au/industry/assetmanagement-branch):

a)         Geotechnical Engineering Report demonstrating that the development has no negative impact on the rail corridor, embankment, or the integrity of the infrastructure.

b)         Excavation and Construction Methodology (including staging) with construction details pertaining to machinery to be used and structural support during excavation. iii. Cross Sectional Drawings showing the rail corridor, sub soil profile, proposed basement excavation and/or structural design of sub ground support adjacent to the rail corridor. All measurements are to be verified by a Registered Surveyor. iv. Detailed Survey Plan showing the relationship of the proposed development with respect to the rail corridor and assets.

c)         If required by Sydney Trains, an FE analysis which assesses the different stages of loading-unloading of the site and its effect on the rock mass surrounding the rail corridor. The Principal Certifying Authority is not to issue the Construction Certificate until written confirmation has been received from Sydney Trains confirming that this condition has been satisfied.

80.        B8.

Prior to the issue of a Construction Certificate, the Applicant shall include in their Construction Management Plan and Safe Working Method Statements (SWMS) adherence to the load restriction set in place for the Pacific Highway Rail Bridge, or as per the applicable structural requirements. The Principal Certifying Authority shall not issue a Construction Certificate until these requirements have been met.

81.        B9.

If required by Sydney Trains, a Track Monitoring Plan (including instrumentation and the monitoring regime during excavation and construction phases) is to be submitted to Sydney Trains for review and endorsement prior to the issuing of a Construction Certificate. The Principal Certifying Authority is not to issue a Construction Certificate until written confirmation has been received from Sydney Trains advising of the need to undertake the track monitoring plan, and if required, that it has been endorsed.

82.        B10.

No work is permitted within the rail corridor (including airspace) or any easements which benefit Sydney Trains/TAHE (Transport Asset Holding Entity), at any time, unless the prior approval of, or an Agreement with, Sydney Trains/TAHE (Transport Asset Holding Entity) has been obtained by the Applicant. The Principal Certifying Authority is not to issue the Construction Certificate until written confirmation has been received from Sydney Trains confirming that this condition has been satisfied.

83.        B11.

A risk analysis, which shall determine the required level of derailment protection (if any), shall be carried out in consultation with Sydney Trains. This risk analysis will determine the redundancy requirements or the minimum collision loads specified in Australian Standard AS5100 that needs to be complied with. The risk assessment is to be prepared in accordance with the Sydney Trains Safety Management System. The Principal Certifying Authority shall not issue the Construction Certificate until it has received written confirmation from Sydney Trains that the risk analysis has been prepared and the Principal Certifying Authority has also confirmed that the measures recommended in this risk analysis have been indicated on the Construction Drawings.

84.        B12.

The Applicant shall prepare an acoustic assessment demonstrating how the proposed development will comply with the Department of Planning’s document titled “Development Near Rail Corridors and Busy Roads- Interim Guidelines”. The Applicant must incorporate in the development all the measures recommended in the report. A copy of the report is to be provided to the Principal Certifying Authority and Council prior to the issuing of a Construction Certificate. The Principal Certifying Authority must ensure that the recommendations of the acoustic assessment are incorporated in the construction drawings and documentation prior to the issuing of the relevant Construction Certificate.

85.        B13.

Prior to the issue of an Occupation Certificate (whether an interim or final Occupation Certificate), a report must be prepared and submitted to the Certifying Authority, Council and Sydney Trains certifying that the completed development meets the requirements of State Environmental Planning Policy (Transport and Infrastructure) 2021 and with the Department of Planning and Infrastructure’s Development Assessment Guideline titled “Development Near Rail Corridors and Busy Roads - Interim Guidelines” as set down in the subject condition of this consent. Such a report must include external and internal noise levels to ensure that the external noise levels during the test are representative of the typical maximum levels that may occur at this development, and that internal noise levels meet the required dB(A) levels. Where it is found that internal noise levels are greater than the required dB(A) level, necessary corrective measures must be carried out to ensure that internal noise levels are compliant with the requirements of this consent.

86.        B14.

Prior to the issue of a Construction Certificate, the Applicant shall undertake a services search to establish the existence and location of any rail services. Persons performing the service search shall use equipment that will not have any impact on rail services and signalling. Should rail services be identified within the subject development site, the Applicant must discuss with Sydney Trains as to whether these services are to be relocated or incorporated within the development site.

87.        B15.

Prior to the issuing of a Construction Certificate, the Applicant must submit to Sydney Trains a final plan showing all craneage and other aerial operations for the development and must comply with all standards and Sydney Trains’ requirements. If required by Sydney Trains, the Applicant must amend the plan showing all craneage and other aerial operations to comply with all Sydney Trains’ requirements. The Principal Certifying Authority is not to issue the Construction Certificate until written confirmation has been received from the Sydney Trains confirming that this condition has been satisfied.

88.        B16.

Prior to the issue of a Construction Certificate the Applicant is to engage an Electrolysis Expert to prepare a report on the Electrolysis Risk to the development from stray currents. The Applicant must incorporate in the development all the measures recommended in the report to control that risk. A copy of the report is to be provided to the Principal Certifying Authority with the application for a Construction Certificate. The Principal Certifying Authority must ensure that the recommendations of the electrolysis report are incorporated in the construction drawings and documentation prior to the issuing of the relevant Construction Certificate.

B17.

No scaffolding is to be used facing the rail corridor and TAHE (Transport Asset Holding Entity) electrical assets unless prior written approval has been obtained from Sydney Trains. To obtain approval the Applicant will be required to submit details of the scaffolding, the means of erecting and securing this scaffolding, the material to be used, and the type of screening to be installed to prevent objects falling onto the rail corridor and TAHE (Transport Asset Holding Entity) electrical assets. Unless agreed to by Sydney Trains in writing, scaffolding shall not be erected without isolation and protection panels.

89.        B18.

Given the possible likelihood of objects being dropped or thrown onto the rail corridor from balconies, windows, and other external features (e.g., roof terraces and external fire escapes) that are within 20 metres of, and face, the rail corridor, the development must have measures installed, to the satisfaction of Sydney Trains (e.g., awning windows, louvres, enclosed balconies, window restrictors etc.) which prevent the throwing of objects onto the rail corridor. The Principal Certifying Authority is not to issue the Construction Certificate until written confirmation has been received from Sydney Trains confirming that this condition has been satisfied.

90.        B19.

The design, installation and use of lights, signs, and reflective materials, whether permanent or temporary, which are (or from which reflected light might be) visible from the rail corridor must limit glare, reflectivity, and illumination to the satisfaction of the rail operator. The Principal Certifying Authority is not to issue the Construction Certificate until written confirmation has been received from Sydney Trains confirming that this condition has been satisfied.

91.        B20.

Prior to the commencement of any works appropriate fencing must be in place along the rail corridor to prevent unauthorised access to the rail corridor during construction works. Details of the type of fencing and the method of erection are to be to the satisfaction of Sydney Trains prior to the fencing work being undertaken.

92.        B21.

The development shall have appropriate fencing fit for the future usage of the development site to prevent unauthorised access to the rail corridor by future occupants of the development. Prior to the issuing of an Occupation Certificate the Applicant shall liaise with Sydney Trains regarding the adequacy of any existing fencing along the rail corridor boundary or design and construction of new fencing. Details of the type of new fencing to be installed and the method of erection are to be to the satisfaction of Sydney Trains prior to the fencing work being undertaken.

93.        B22.

The Applicant is to ensure that the development incorporates appropriate anti-graffiti measures, to the satisfaction of Sydney Trains.

94.        B23.

The Applicant must ensure that all drainage from the development is adequately disposed of and managed and not allowed to be discharged into the rail corridor unless prior written approval has been obtained from Sydney Trains.

95.        B24.

Rainwater from the roof must not be projected and/or falling into the rail corridor and must be piped down the face of the building which faces the rail corridor.

96.        B25.

During all stages of the development the Applicant must take extreme care to prevent any form of pollution entering the rail corridor. Any form of pollution that arises as a consequence of the development activities shall remain the full responsibility of the Applicant.

97.        B26.

Excess soil is not allowed to enter, be spread, or stockpiled within the rail corridor (and its easements) and must be adequately managed/disposed of.

98.        B27.

Sydney Trains advises there are 11kV & 33kV High Voltage Aerial Transmission Lines in close proximity to the proposed works. All works within 6 metres of the nearest transmission line conductor must comply with:

a)         ISSC 20 - Guideline for the Management of Activities within Electricity Easements and Close to Electricity Infrastructure.

b)         The Safe Approach Distances (SADs) in the Sydney Trains Document titled “SMS06-GD-0268 - Working Around Electrical Equipment”.

c)         “WorkCover Code of Practice - Work near Overhead Power Lines (The Code)” B28. There is a need to ensure that the roots and foliage of trees being planted beside the rail corridor and High Voltage Aerial Transmission Line(s) do not have an impact on the rail corridor, rail operations, or infrastructure assets. All Landscaping shall be in accordance with the Sydney Trains High Voltage Powerline Tree Management Plan. A final landscaping and planting plan demonstrating measures to ensure compliance with this condition must be prepared to the satisfaction of Sydney Trains. No construction certificate can be issued until written confirmation has been received from Sydney Trains confirming that this condition has been complied with.

99.        B29.

No metal ladders, tapes, and plant, machinery, or conductive material are to be used within 6 horizontal metres of any live electrical equipment. This applies to the train pantographs and catenary, contact and pull-off wires of the adjacent tracks, and to any aerial power supplies within or adjacent to the rail corridor.

100.      B30.

If required by Sydney Trains, prior to the issue of a Construction Certificate, a Risk Assessment/Management Plan, and detailed Safe Work Method Statements (SWMS) for the proposed works are to be submitted to Sydney Trains for review and comment on the impacts on rail corridor. The Principal Certifying Authority is not to issue the Construction Certificate until written confirmation has been received from Sydney Trains confirming that this condition has been satisfied.

101.      B31.

No metal ladders, tapes, and plant, machinery, or conductive material are to be used within 6 horizontal metres of any live electrical equipment. This applies to the train pantographs and catenary, contact and pull-off wires of the adjacent tracks, and to any aerial power supplies within or adjacent to the rail corridor.

102.      B32.

Prior to the issuing of any Occupation Certificate, the Applicant must provide to Sydney Trains for review and endorsement a plan of how future maintenance of the development facing the rail corridor is to be undertaken. The Principal Certifying Authority is not to issue any Occupation Certificate until written confirmation has been received from Sydney Trains confirming that this condition has been satisfied. The maintenance plan must be implemented for the life of the approved development.

103.      B33.

Prior to the issuing of any Occupation Certificate, the Applicant is to submit as-built drawings to Sydney Trains and Council. The as-built drawings are to be endorsed by a Registered Surveyor confirming that there has been no encroachment into TAHE (Transport Asset Holding Entity) property or easements, unless agreed to by TAHE (Transport Asset Holding Entity). The Principal Certifying Authority is not to issue the final Occupation Certificate until written confirmation has been received from Sydney Trains confirming that this condition has been satisfied.

104.      B34.

If required by Sydney Trains, prior to the commencement of works or at any time during the excavation and construction period deemed necessary by Sydney Trains, a joint inspection of the rail infrastructure and property in the vicinity of the project is to be carried out by representatives from Sydney Trains and the Applicant. These dilapidation surveys will establish the extent of any existing damage and enable any deterioration during construction to be observed. The submission of a detailed dilapidation report will be required within 10 days following the undertaking of the inspection, unless otherwise notified by Sydney Trains.

105.      B35.

If required by Sydney Trains, prior to the issue of the Occupation Certificate, or at any time during the excavation and construction period deemed necessary by Sydney Trains, a joint inspection of the rail infrastructure and property in the vicinity of the project is to be carried out by representatives from Sydney Trains and the Applicant. These dilapidation surveys will establish the extent of any existing damage and enable any deterioration during construction to be observed. The Principal Certifying Authority is not to issue the final Occupation Certificate until written confirmation has been received from Sydney Trains confirming that this condition has been satisfied.

106.      B36.

If required, prior to the issue of a Construction Certificate the Applicant is to contact Sydney Trains External Interface Management team to determine the need for the lodgement of a Bond or Bank Guarantee for the duration of the works. The Bond/Bank Guarantee shall be for the sum determined by Sydney Trains. Prior to issuing the Construction Certificate the Principal Certifying Authority must witness written advice from Sydney Trains confirming the lodgement of this Bond/Bank Guarantee.

107.      B37.

If required, prior to the issue of a Construction Certificate the Applicant is to contact Sydney Trains External Interface Management team to determine the need for public liability insurance cover. If insurance cover is deemed necessary, this insurance must be for a sum as determined by Sydney Trains and shall not contain any exclusion in relation to works on or near the rail corridor and rail infrastructure, and must be maintained for the duration specified by Sydney Trains. The Applicant is to contact Sydney Trains External Interface Management team to obtain the level of insurance required for this particular proposal. Prior to issuing the Construction Certificate the Principal Certifying Authority must witness written proof of this insurance in conjunction with Sydney Trains’ written advice to the Applicant on the level of insurance required.

108.      B38.

Sydney Trains or Transport for NSW, and persons authorised by those entities for the purpose of this condition, must be permitted to inspect the site of the development and all structures to enable it to consider whether those structures have been or are being constructed and maintained in accordance with the approved plans and the requirements of this consent, on giving reasonable notice to the principal contractor for the development or the owner or occupier of the part of the site to which access is sought.

109.      B39.

The Applicant must ensure that at all times they have a representative (which has been notified to Sydney Trains in writing), who:

a)         oversees the carrying out of the Applicant’s obligations under the conditions of this consent and in accordance with correspondence issued by Sydney Trains;

b)         acts as the authorised representative of the Applicant; and

c)         is available (or has a delegate notified in writing to Sydney Trains that is available) on a 7 day a week basis to liaise with the representative of Sydney Trains, as notified to the Applicant.

110.      B40.

Without in any way limiting the operation of any other condition of this consent, the Applicant must, during demolition, excavation and construction works, consult in good faith with Sydney Trains in relation to the carrying out of the development works and must respond or provide documentation as soon as practicable to any queries raised by Sydney Trains in relation to the works.

111.      B41.

Where a condition of consent requires consultation with Sydney Trains, the Applicant shall forward all requests and/or documentation to the relevant Sydney Trains External Interface Management team. In this instance the relevant interface team is North Interface, and they can be contacted via email on North_Interface@transport.nsw.gov.au.

112.      B42.

Copies of any certificates, drawings, approvals/certification, or documents endorsed by, given to, or issued by Sydney Trains or TAHE (Transport Asset Holding Entity) must be submitted to Council for its records prior to the issuing of the applicable Construction Certificate or Occupation Certificate.

113.      B43.

Where a condition of consent requires Sydney Trains or Transport for NSW endorsement the Principal Certifying Authority is not to issue a Construction Certificate or Occupancy Certificate, as the case may be, until written confirmation has been received from those entities that the particular condition has been complied with. The issuing of staged Construction Certificates dealing with specific works and compliance conditions can be issued subject to written agreement from those entities to which the relevant conditions applies.

- END OF CONDITIONS -

ADVISORY NOTES

The following information is provided for your assistance to ensure compliance with the Environmental Planning and Assessment Act 1979, Environmental Planning and Assessment Regulation 2021, other relevant legislation and Council’s policies and specifications.  This information does not form part of the conditions of development consent pursuant to Section 4.17 of the Act.

Environmental Planning and Assessment Act 1979 Requirements

The Environmental Planning and Assessment Act 1979 requires:

·              The issue of a construction certificate prior to the commencement of any works.  Enquiries can be made to Council’s Customer Services Branch on 9847 6760.

·              A principal certifying authority to be nominated and Council notified of that appointment prior to the commencement of any works.

·              Council to be given at least two days written notice prior to the commencement of any works.

·              Mandatory inspections of nominated stages of the construction inspected.

·              An occupation certificate to be issued before occupying any building or commencing the use of the land.

Long Service Levy 

In accordance with Section 34 of the Building and Construction Industry Long Service Payments Act 1986, a ‘Long Service Levy’ must be paid to the Long Service Payments Corporation or Hornsby Council.

Note:  The rate of the Long Service Levy is 0.35% of the total cost of the work.

Note:  Hornsby Council requires the payment of the Long Service Levy prior to the issue of a construction certificate.

Tree and Vegetation Preservation

Hornsby Development Control Plan 2013 Tree and Vegetation Preservation provisions have been developed under Council’s authorities contained in State Environmental Planning Policy (Biodiversity and Conservation) 2021 and the Environmental Planning and Assessment Act 1979.

In accordance with these provisions a person must not cut down, fell, uproot, kill, poison, ringbark, burn or otherwise destroy the vegetation, lop or otherwise remove a substantial part of the trees or vegetation to which any such development control plan applies without the authority conferred by a development consent or a permit granted by Council.

Fines may be imposed for non-compliance with the Hornsby Development Control Plan 2013.

Note: A tree is defined as a long lived, woody perennial plant with one or relatively few main stems with the potential to grow to a height greater than three metres (3m). (HDCP 1B.6.1.c).

Disability Discrimination Act

The applicant’s attention is drawn to the existence of the Disability Discrimination Act 1992.  A construction certificate is required to be obtained for the proposed building/s, which will provide consideration under the Building Code of Australia, however, the development may not comply with the requirements of the Disability Discrimination Act 1992.  This is the sole responsibility of the applicant.

Covenants

The land upon which the subject building is to be constructed may be affected by restrictive covenants.  Council issues this approval without enquiry as to whether any restrictive covenant affecting the land would be breached by the construction of the building, the subject of this consent.  Applicants must rely on their own enquiries as to whether or not the building breaches any such covenant.

Tenancy Fit-Out - Separate DA Required

This consent does not permit the fit-out of individual tenancies.  A separate development application is required for the fit-out of individual tenancies prior to the occupation of the building.

Use of Building - Separate DA Required

This consent does not permit the use of the premises for any purpose.  Separate development consent is required for the use of the premises prior to the occupation of the building.

Advertising Signage - Separate DA Required

This consent does not permit the erection or display of any advertising signs.  Most advertising signs or structures require development consent.  Applicants should make separate enquiries with Council prior to erecting or displaying any advertising signage.

Dial Before You Dig

Prior to commencing any works, the applicant is encouraged to contact Dial Before You Dig on 1100 or www.dialbeforeyoudig.com.au for free information on potential underground pipes and cables within the vicinity of the development site.

Telecommunications Act 1997 (Commonwealth)

If you are aware of any works or proposed works which may affect or impact on Telstra’s assets in any way, you are required to contact: Telstra’s Network Integrity Team on Phone Number 1800810443.

Asbestos Warning

Should asbestos or asbestos products be encountered during demolition or construction works, you are advised to seek advice and information prior to disturbing this material. It is recommended that a contractor holding an asbestos-handling permit (issued by SafeWork NSW) be engaged to manage the proper handling of this material. Further information regarding the safe handling and removal of asbestos can be found at:

www.environment.nsw.gov.au

www.adfa.org.au

www.safework.nsw.gov.au

Alternatively, telephone the SafeWork NSW on 13 10 50.

Construction Traffic Management Plan Advisory Note (TfNSW)

·              Any bus seating readjustments will require approval from the relevant assets owner (council and/or Rail) and must comply to TFNSW and Bus operator guidelines.

·              For the class B hoarding, they will need to ensure that along the Pacific Hwy it is a minimum 600mm from the kerb, preferably 800mm from the kerb to ensure safety clearance for buses is met.

·              Any Traffic Guidance Schemes (TGS) prepared are to comply with AS1742.3 and Transport for NSW’s "Traffic Control at Worksites" manual and be signed by a person with TfNSW certification to prepare a TGS.

·              Proponent must apply and obtain approval from the Transport Management Centre for a Road Occupancy Licence (ROL) for any required lane closures and/or Speed Zone Authorisations as part of the ROL that impact the state road network or is within 100m of traffic signals.

·              Proponent must submit a site specific traffic management plan for any Road closures required to Road occupancy unit for endorsement.

·              No marshalling or queuing of construction vehicles is to occur on public roads. Arriving vehicles that are not able to use parking bay/work zone must continue to a holding point until space becomes available.

·              When heavy vehicles are entering or leaving the site a traffic controller is to be provided to manage any conflicts between pedestrians and heavy vehicles.

·              Transport for New South Wales reserve the right to alter the CTMP Conditions at any time to maintain safe and efficient traffic and pedestrian movements in this area

·              Any approved Works Zone should only be used for work activities. No infrastructure, including bins, tanks or traffic control equipment should be left on the road when the works zone is not in use by a vehicle. All non-vehicular items must be contained with the work area and not on the carriageway. When a work zone is not in use, the area/lane must be opened up to allow for normal trafficable conditions

·              Should TfNSW Network and Asset Management, Network Operations, CJP Operations, Network and Safety or other TfNSW business area determine that that more information is to be provided for review and acceptance, including other TCS locations, this information must be submitted prior to the CTMP being implemented, or otherwise agreed upon.

·              Endorsement of the CTMP is not an approval to the type of traffic management or delineation devices used, nor is it an approval to any traffic guidance schemes depicted within the CTMP. It is assumed that the proponent has used type approved devices and has developed its traffic guidance schemes in accordance with the relevant Australian Standards and Guidelines.

·              The proponent is to ensure local residents, businesses, schools and other stakeholders in the affected area as well as emergency service organisations are notified of the changes associated with the CTMP, prior to its implementation.

·              Please ensure this CTMP is shared and adhered to by all contractors. If the CTMP changes, please forward a copy to Developments.CJP@transport.nsw.gov.au or further review and endorsement.

 


Hornsby Shire Council

Attachment to Report No. LPP55/22 Page 1

 

Diagram

Description automatically generated


Hornsby Shire Council

Attachment to Report No. LPP55/22 Page 67

 


Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Diagram

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Table

Description automatically generated

Table

Description automatically generated

Table

Description automatically generated

A screenshot of a computer

Description automatically generated with low confidence

Text

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text

Description automatically generated

Text

Description automatically generated

Text

Description automatically generated

Text

Description automatically generated

Text

Description automatically generated

Text

Description automatically generated

Text

Description automatically generated

Text, letter

Description automatically generated

Text

Description automatically generated

Text

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text

Description automatically generated

Text, letter

Description automatically generated

Text

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated


Hornsby Shire Council

Attachment to Report No. LPP55/22 Page 71

 


Text, letter

Description automatically generated

Text

Description automatically generated

Diagram

Description automatically generated

Text, letter

Description automatically generated


Hornsby Shire Council

Attachment to Report No. LPP55/22 Page 89

 


Text

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated


Hornsby Shire Council

Attachment to Report No. LPP55/22 Page 108

 


Text

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text, letter

Description automatically generated

Text

Description automatically generated

Text, letter

Description automatically generated

Text

Description automatically generated

A picture containing text

Description automatically generated


Hornsby Shire Council

Attachment to Report No. LPP55/22 Page 156

 


Diagram, engineering drawing

Description automatically generated

Diagram, engineering drawing, schematic

Description automatically generated

Diagram, engineering drawing, schematic

Description automatically generated

Diagram, engineering drawing

Description automatically generated

A picture containing graphical user interface

Description automatically generated

A picture containing chart

Description automatically generated

Diagram, engineering drawing

Description automatically generated

Diagram, engineering drawing

Description automatically generated

Diagram, engineering drawing

Description automatically generated

Diagram

Description automatically generated

Diagram

Description automatically generated with medium confidence

Diagram, engineering drawing

Description automatically generated

Diagram

Description automatically generated

Diagram

Description automatically generated

Diagram

Description automatically generated

Diagram, engineering drawing

Description automatically generated

Diagram, engineering drawing

Description automatically generated

Diagram, engineering drawing

Description automatically generated

Diagram, engineering drawing

Description automatically generated

Calendar

Description automatically generated

Diagram, engineering drawing, schematic

Description automatically generated

Diagram, engineering drawing

Description automatically generated

Diagram, schematic

Description automatically generated

Diagram

Description automatically generated with medium confidence

Diagram

Description automatically generated with low confidence

Diagram

Description automatically generated

Diagram, schematic

Description automatically generated

Diagram, schematic

Description automatically generated

Diagram

Description automatically generated

Diagram

Description automatically generated

Diagram

Description automatically generated

Diagram

Description automatically generated

Diagram

Description automatically generated

Diagram

Description automatically generated

Diagram

Description automatically generated

Diagram

Description automatically generated

Diagram

Description automatically generated

Diagram

Description automatically generated

Diagram

Description automatically generated

Diagram

Description automatically generated

Diagram

Description automatically generated

Diagram

Description automatically generated

Diagram

Description automatically generated

Diagram

Description automatically generated

Diagram

Description automatically generated

Diagram

Description automatically generated

Diagram

Description automatically generated

Diagram

Description automatically generated


Hornsby Shire Council

Attachment to Report No. LPP55/22 Page 162

 


Diagram, engineering drawing

Description automatically generated

Diagram, engineering drawing

Description automatically generated

Diagram, engineering drawing

Description automatically generated

Diagram, engineering drawing

Description automatically generated

Diagram

Description automatically generated

Diagram, schematic

Description automatically generated